Contracts & ExecutionQuestion 705 of 1632

Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?

a.The homeowner must be a senior citizen
b.The contractor must be paid in full in advance
c.The contract price must exceed $2,500
d.The buyer must have initiated contact requesting the work

Explanation

Under B&P §7159.10, a service and repair contract may be used only when, among other conditions, the buyer initiated contact to request the work and the price is $750 or less.

Law Reference: B&P §7159.10

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report