Contracts & ExecutionQuestion 705 of 1605

Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?

a.The homeowner must be a senior citizen
b.The contractor must be paid in full in advance
c.The contract price must exceed $2,500
d.The buyer must have initiated contact requesting the work

Explanation

Under B&P §7159.10, a service and repair contract may be used only when, among other conditions, the buyer initiated contact to request the work and the price is $750 or less.

Law Reference: B&P §7159.10