Obras PúblicasPregunta 1589 de 1605
When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:
a.Only fringe benefits
b.Only the base hourly cash wage
c.The contractor's overhead and profit
d.The basic hourly rate PLUS employer payments for benefits such as health, pension, vacation, and training
Explicación
Prevailing 'per diem wages' (Labor Code §1773) include the basic hourly rate plus employer payments for fringe benefits — health and welfare, pension, vacation/holiday, and apprenticeship training contributions. Contractors must account for both the cash wage and the benefit components.
Referencia Legal: Labor Code §1773Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that:
- On a public works project, a 'bid bond' submitted with a contractor's bid primarily guarantees that:
- Failure to comply with apprenticeship requirements on a covered public works project can result in:
- 'Debarment' in the public works context means a contractor is:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)