Obras PúblicasPregunta 1591 de 1605
Failure to comply with apprenticeship requirements on a covered public works project can result in:
a.A refund of the contractor's registration fee
b.No consequence, since apprenticeship is voluntary
c.An automatic increase in the contract price
d.Civil penalties and possible debarment from bidding on public works
Explicación
Labor Code §1777.7 authorizes civil penalties and, for knowing violations, debarment (ineligibility to bid on or work public works for a period) for failing to comply with apprenticeship requirements. Apprenticeship compliance is mandatory on covered public works.
Referencia Legal: Labor Code §1777.7Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that:
- When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:
- On a public works project, a 'bid bond' submitted with a contractor's bid primarily guarantees that:
- 'Debarment' in the public works context means a contractor is:
- If the Labor Commissioner issues a Civil Wage and Penalty Assessment for prevailing wage violations, the contractor generally may:
- A public agency rejects the lowest bid because the bidder failed to acknowledge a required addendum and omitted a mandatory subcontractor listing. This bid was properly rejected as:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)