A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:

a.Wait for the awarding body to pay it out of retention
b.Record a mechanics lien against the public building
c.Obtain the public agency's written approval to be paid
d.Give any required notice and sue on the bond in time

Explicación

Because public property cannot be liened, the unpaid subcontractor's security is the prime's payment bond: it must give any preliminary notice its position requires and then sue on the bond, which Civil Code §9558 allows any time after it stops work but no later than six months after the stop-notice period in §9356 closes. Recording a lien against the school or city building is void from the start. Retention is money owed the prime under the prime contract, not a fund the agency pays claimants from. No agency consent is needed or available; the bond is a contract with the surety.

Referencia Legal: Civil Code §9558; §9356

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar