Obras PúblicasPregunta 1600 de 1632
DIR public works contractor registration generally must be:
a.Waived for any contractor with a current CSLB licence
b.Obtained once and carried for the life of the business
c.Renewed annually and kept current to bid and to perform
d.Obtained separately for each public works contract
Explicación
Labor Code §1725.5 makes DIR public works registration an annual registration with an annual fee, and it must be current at the moment the contractor bids, is listed on a bid, is awarded work, or performs. A CSLB licence is a separate requirement and waives nothing. A one-time registration would defeat the annual fee the statute imposes. Registration attaches to the contractor, not to the job, so one current registration covers every covered project rather than being repeated contract by contract.
Referencia Legal: Labor Code §1725.5(a)Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- The performance bond on a public works project protects the:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
- On a public works project, the prevailing wage obligation applies to:
Última revisión: · proceso editorial
Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)