Seguros y GravámenesPregunta 1487 de 1605
A recorded mechanics lien claim in California must include, among other things, a statement of the claimant's demand, the name of the owner, a description of the site, and:
a.The owner's Social Security number
b.The claimant's federal tax return
c.A proof of service affidavit showing the lien was served on the owner
d.A copy of the building permit
Explicación
Civil Code §8416 requires the mechanics lien to contain specified content and, importantly, be served on the owner with a proof of service affidavit. Failure to serve the owner and attach the proof of service can render the lien unenforceable.
Referencia Legal: Civ. Code §8416Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- When a prime contractor is named as an 'additional insured' on a subcontractor's CGL policy, the practical benefit to the prime is that:
- Which statement best distinguishes a SURETY BOND from an INSURANCE policy?
- An indemnity (hold-harmless) clause in a construction subcontract typically operates to:
- Under current California law, a mechanics lien is generally NOT enforceable unless the claimant:
- An owner who learns that work is being done on their property without their authorization (e.g., by a tenant) can limit exposure to mechanics liens by recording and posting a:
- To be effective, a Notice of Non-Responsibility must generally be posted on the property and recorded within how many days after the owner obtains knowledge of the work of improvement?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)