Seguros y GravámenesPregunta 1489 de 1605
An owner who learns that work is being done on their property without their authorization (e.g., by a tenant) can limit exposure to mechanics liens by recording and posting a:
a.Stop payment notice
b.Preliminary notice
c.Notice of completion
d.Notice of non-responsibility
Explicación
Civil Code §8444 (Notice of Non-Responsibility) lets an owner who did not cause the work and does not want to be responsible protect their interest by posting and recording the notice within 10 days of learning of the work. It is commonly used when a tenant orders improvements.
Referencia Legal: Civ. Code §8170Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- An indemnity (hold-harmless) clause in a construction subcontract typically operates to:
- A recorded mechanics lien claim in California must include, among other things, a statement of the claimant's demand, the name of the owner, a description of the site, and:
- Under current California law, a mechanics lien is generally NOT enforceable unless the claimant:
- To be effective, a Notice of Non-Responsibility must generally be posted on the property and recorded within how many days after the owner obtains knowledge of the work of improvement?
- Which event does NOT constitute 'completion' of a work of improvement for purposes of starting mechanics lien deadlines on a private project?
- A 'notice of cessation' may be recorded by an owner when labor has ceased on the work of improvement for a continuous period of at least:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)