Seguros y GravámenesPregunta 1496 de 1605
The 20-day period for serving a Preliminary Notice generally begins to run from the date the claimant:
a.Records its mechanics lien
b.First furnishes labor, service, equipment, or materials to the project
c.Receives its first progress payment
d.Signs its subcontract
Explicación
Civil Code §8200 measures the 20-day period from when the claimant first provides work to the project. Notice given more than 20 days after first furnishing limits lien/stop-notice rights to work provided within 20 days before service and thereafter.
Referencia Legal: Civ. Code §8200Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- The party who purchases a surety bond and whose performance is guaranteed is called the:
- On a bond, the party who is protected and can make a claim if the principal defaults is the:
- An owner or contractor who wants to remove a recorded mechanics lien from title while still disputing the claim may record a:
- Which of the following is the BEST reason a general contractor requires subcontractors to name it as an additional insured and provide certificates of insurance?
- If a contractor illegally fails to carry required workers' compensation insurance and an employee is injured, the employee may:
- What is a direct consequence for a licensed contractor whose required workers' compensation insurance lapses?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)