Seguros y GravámenesPregunta 1546 de 1605
On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?
a.30 days from completion
b.60 days from completion
c.One year from completion
d.90 days from completion
Explicación
When no notice of completion or cessation is recorded, Civil Code §8412 and §8414 give every claimant 90 days after actual completion to record a mechanics lien. The 30/60-day distinctions apply only once such a notice is recorded.
Referencia Legal: Civ. Code §8412Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
- California Civil Code §2782 generally makes VOID a construction contract provision that requires one party to indemnify another for the latter's:
- A 'primary and noncontributory' insurance requirement in a subcontract means that when the sub names the GC as additional insured, the sub's policy should:
- Why might an owner prefer that the general contractor obtain a payment bond rather than rely solely on the contractor to pay subs?
- 'Inland marine' insurance for a contractor most commonly covers:
- An equipment rental company rents a crane to a subcontractor on a private project. To preserve a mechanics lien for unpaid rental charges, the rental company should:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)