Seguros y GravámenesPregunta 1549 de 1605
An equipment rental company rents a crane to a subcontractor on a private project. To preserve a mechanics lien for unpaid rental charges, the rental company should:
a.Do nothing, since equipment lessors have automatic liens
b.Serve notice only on the subcontractor
c.Serve a preliminary notice on the owner, direct contractor, and construction lender within 20 days of first furnishing
d.Record a lien before delivering the crane
Explicación
Equipment lessors that provide equipment for a work of improvement have lien rights but, lacking a direct owner contract, must serve a preliminary notice on the owner, direct contractor, and lender within 20 days of first furnishing under Civil Code §8200 to preserve those rights.
Referencia Legal: Civ. Code §8200Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?
- Why might an owner prefer that the general contractor obtain a payment bond rather than rely solely on the contractor to pay subs?
- 'Inland marine' insurance for a contractor most commonly covers:
- The primary function of a 'certificate of insurance' in the contracting process is to allow one party to:
- Under California's workers' compensation system, an employee injured on the job generally receives benefits:
- A contractor's 'umbrella' or 'excess' liability policy is designed to:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)