Seguros y GravámenesPregunta 1549 de 1605

An equipment rental company rents a crane to a subcontractor on a private project. To preserve a mechanics lien for unpaid rental charges, the rental company should:

a.Do nothing, since equipment lessors have automatic liens
b.Serve notice only on the subcontractor
c.Serve a preliminary notice on the owner, direct contractor, and construction lender within 20 days of first furnishing
d.Record a lien before delivering the crane

Explicación

Equipment lessors that provide equipment for a work of improvement have lien rights but, lacking a direct owner contract, must serve a preliminary notice on the owner, direct contractor, and lender within 20 days of first furnishing under Civil Code §8200 to preserve those rights.

Referencia Legal: Civ. Code §8200

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar