Which of the following must a home improvement contract include regarding the work to be done?
Explicación
B&P §7159(d)(7) requires the heading 'Description of the Project and Description of the Significant Materials to be Used and Equipment to be Installed', followed by that description. It is what makes the scope enforceable and what any change order has to be measured against. (b) is the bare-price contract the statute exists to outlaw; the price is required too (§7159(d)(5)), but a price with no described scope is not a compliant contract. (d) leaves the scope oral, which is exactly what §7159(d) forbids. (c) is required nowhere and solves nothing: §7159.5(a)(5) bars accepting payment beyond the value in place, so a wire authorization is no substitute for a payment schedule.
Referencia Legal: Bus. & Prof. Code §7159(d)(5), (7); §7159.5(a)(5)Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- A homeowner calls a plumber for an urgent $400 leak repair. The plumber may use a service and repair contract only if, among other conditions, the plumber:
- Failing to give the homeowner a copy of the signed home improvement contract is:
- A contractor pre-prints the contract 'date' as the day AFTER the actual signing to shorten the buyer's cancellation window. This is:
- A valid service and repair contract must still give the buyer:
- On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
Última revisión: · proceso editorial