On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
a.$5,000
b.$1,000
c.$2,500
d.$500
Explicación
The cap is $1,000 or 10%, whichever is less. Ten percent of $50,000 is $5,000, but the $1,000 ceiling is lower, so the maximum lawful down payment is $1,000.
Referencia Legal: B&P §7159(d)Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A contractor pre-prints the contract 'date' as the day AFTER the actual signing to shorten the buyer's cancellation window. This is:
- Which of the following must a home improvement contract include regarding the work to be done?
- A valid service and repair contract must still give the buyer:
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
- The three-day right to cancel a home improvement contract applies primarily to contracts that are:
- The 'Notice to Owner' that must accompany a home improvement contract primarily explains:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)