Contratos y EjecuciónPregunta 732 de 1605
The 'Notice to Owner' that must accompany a home improvement contract primarily explains:
a.The resale value of the home
b.The contractor's insurance policy limits
c.How to obtain a building permit
d.The owner's rights and responsibilities under the mechanics lien laws
Explicación
The Notice to Owner required with home improvement contracts educates the property owner about the mechanics lien laws and the risk that unpaid subcontractors or suppliers could lien the property.
Referencia Legal: B&P §7159(c)Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
- The three-day right to cancel a home improvement contract applies primarily to contracts that are:
- A contractor's payment schedule requires the owner to pay 80% of the price before any materials arrive or work begins. This violates §7159 because:
- Which scenario would DISQUALIFY a job from using the service and repair contract form?
- The required title 'Home Improvement' and the mandatory notices in a §7159 contract must be presented in a way that is:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)