A contractor's payment schedule requires the owner to pay 80% of the price before any materials arrive or work begins. This violates §7159 because:
Explicación
B&P §7159.5(a)(5) is the rule: except for the downpayment, the contractor 'shall neither request nor accept payment that exceeds the value of the work performed or material delivered', and the bar extends to advance payment in whole or in part from any lender or financier. Eighty percent before anything arrives on site fails that test on day one, and §7159.5(a)(3) separately caps the downpayment at $1,000 or 10 percent of the contract amount, whichever is less. (a) restates the violation as if it were the cure. (d) invents an equal-instalment rule; §7159.5(a)(4) requires each payment to reference the work it buys, which almost never produces equal amounts. (c) invents a cash requirement, which would defeat the joint-check protection the Mechanics Lien Warning urges on the owner.
Referencia Legal: Bus. & Prof. Code §7159.5(a)(3)-(5)Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
- The three-day right to cancel a home improvement contract applies primarily to contracts that are:
- The 'Notice to Owner' that must accompany a home improvement contract primarily explains:
- Which scenario would DISQUALIFY a job from using the service and repair contract form?
- The required title 'Home Improvement' and the mandatory notices in a §7159 contract must be presented in a way that is:
- A home improvement contract must state the total price the buyer will pay, described as the:
Última revisión: · proceso editorial