Contratos y EjecuciónPregunta 737 de 1605

If a home improvement contract fails to contain the elements required by §7159, the contractor may be subject to:

a.Disciplinary action against the license by the CSLB
b.A federal tax lien
c.Automatic criminal imprisonment with no hearing
d.No consequences at all

Explicación

Violations of the home improvement contract requirements of B&P §7159 are grounds for disciplinary action by the CSLB against the contractor's license.

Referencia Legal: B&P §7159

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)