Contratos y EjecuciónPregunta 738 de 1605
To cancel within the three-day period, the buyer must:
a.Get the contractor's written permission
b.Appear in person at the CSLB office
c.Wait until work is 50% complete
d.Send or deliver written notice of cancellation by midnight of the third business day
Explicación
The buyer exercises the right to cancel by giving written notice (for example, mailing the cancellation form) by midnight of the third business day after signing.
Referencia Legal: Civil Code §1689.7Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- The required title 'Home Improvement' and the mandatory notices in a §7159 contract must be presented in a way that is:
- A home improvement contract must state the total price the buyer will pay, described as the:
- If a home improvement contract fails to contain the elements required by §7159, the contractor may be subject to:
- Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?
- For a service and repair contract, the buyer must receive a fully completed copy:
- A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos