Contratos y EjecuciónPregunta 739 de 1605

Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?

a.A notice that the buyer is entitled to a completely filled-in copy of the contract before work begins
b.A statement that the buyer waives all rights
c.The contractor's blood type
d.The name of the salesperson's supervisor only

Explicación

B&P §7159 requires notice language ensuring the buyer receives a fully completed copy of the signed contract before work begins and understands their rights, including the right to cancel.

Referencia Legal: B&P §7159(c)