Contratos y EjecuciónPregunta 739 de 1605
Which of the following must appear near the buyer's signature line as a required caution in a home improvement contract?
a.A notice that the buyer is entitled to a completely filled-in copy of the contract before work begins
b.A statement that the buyer waives all rights
c.The contractor's blood type
d.The name of the salesperson's supervisor only
Explicación
B&P §7159 requires notice language ensuring the buyer receives a fully completed copy of the signed contract before work begins and understands their rights, including the right to cancel.
Referencia Legal: B&P §7159(c)Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A home improvement contract must state the total price the buyer will pay, described as the:
- If a home improvement contract fails to contain the elements required by §7159, the contractor may be subject to:
- To cancel within the three-day period, the buyer must:
- For a service and repair contract, the buyer must receive a fully completed copy:
- A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:
- The down payment and progress payment limits in §7159 are designed primarily to:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)