Contratos y EjecuciónPregunta 741 de 1605

A contractor completes 40% of a $20,000 job. Under §7159, the maximum he may have collected by that point (excluding a lawful down payment) is generally:

a.Nothing until 100% complete
b.$15,000
c.About the value of the work performed and materials delivered, roughly $8,000
d.The full $20,000

Explicación

Progress payments may not exceed the value of work performed and materials delivered. At 40% completion, collections should track roughly that value, about $8,000, plus any lawful down payment.

Referencia Legal: B&P §7159(d)