Contratos y EjecuciónPregunta 740 de 1605

For a service and repair contract, the buyer must receive a fully completed copy:

a.Never; it is optional
b.Before any work commences
c.Only after payment
d.Within 30 days of completion

Explicación

As with home improvement contracts, B&P §7159.10 requires the contractor to give the buyer a completed copy of the service and repair contract before work begins.

Referencia Legal: B&P §7159.10

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar