A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
Giải thích
Labor Code §1776(h) gives the contractor 10 days after a written request and then forfeits $100 for each calendar day, or part of one, for each worker, until strict compliance; those penalties are withheld from progress payments at the Division's request. Withholding is limited to the penalty amount, so the whole progress payment is not lost. Nothing about a records failure extends the completion date. The CSLB is not the assessing body here, and it is not the only one that can act: on a DIR-monitored job §1771.4(a)(3)(B) adds its own $100-a-day penalty, capped at $5,000 for the project.
Trích dẫn luật: Labor Code §1776(h); §1771.4(a)(3)(B)Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- A public agency rejects the lowest bid because the bidder failed to acknowledge a required addendum and omitted a mandatory subcontractor listing. This bid was properly rejected as:
- Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:
- A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
Cập nhật gần nhất: · quy trình kiểm tra