Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:

a.Payment of prevailing wages to the listed subcontractors
b.The prime from self-performing any part of the work
c.Bid shopping and bid peddling after the award
d.Unlicensed subcontractors from working on public jobs

Giải thích

The Subletting and Subcontracting Fair Practices Act makes the prime name, in its bid, every subcontractor whose work exceeds one-half of one percent of the total bid, so the prime cannot shop those prices down after award or let rivals peddle lower ones in. Prevailing wage duties come from Labor Code §1771 and apply whether or not a sub is listed. Self-performance is not restricted by the Act; listing is required only for work actually subcontracted. Licensing is policed by the CSLB and by §4104's licence-number requirement, which is a detail of listing rather than its purpose.

Trích dẫn luật: Public Contract Code §4104; §4107

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi