A public agency rejects the lowest bid because the bidder failed to acknowledge a required addendum and omitted a mandatory subcontractor listing. This bid was properly rejected as:

a.An alternate bid the agency may accept at its option
b.The lowest responsible bid, which the agency must take
c.A responsive bid with a minor irregularity to waive
d.Nonresponsive, for failing a material bid requirement

Giải thích

A bid that misses a material requirement of the solicitation is nonresponsive and may be rejected however low it is; failing to acknowledge an addendum and omitting the subcontractor listing required by Public Contract Code §4104 are both material. An alternate bid is a priced option the agency itself invited, not a defective base bid. Calling it the lowest responsible bid confuses responsibility, which is about the bidder's capacity, with responsiveness, which is about the bid document. An agency may waive only an immaterial irregularity, and an omitted sub list is not one.

Trích dẫn luật: Public Contract Code §4104; §4106

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi