A public agency rejects the lowest bid because the bidder failed to acknowledge a required addendum and omitted a mandatory subcontractor listing. This bid was properly rejected as:
a.An alternate bid
b.The lowest responsible bid
c.A responsive bid
d.Nonresponsive, because it did not conform to the material requirements of the solicitation
Giải thích
A bid that fails to comply with material requirements — such as acknowledging addenda or listing subcontractors as required — is 'nonresponsive' and may be rejected even if lowest in price. Responsiveness concerns whether the bid conforms to the bidding documents.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Failure to comply with apprenticeship requirements on a covered public works project can result in:
- 'Debarment' in the public works context means a contractor is:
- If the Labor Commissioner issues a Civil Wage and Penalty Assessment for prevailing wage violations, the contractor generally may:
- Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:
- A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)