保险与留置权第 1496 / 1632 题

The 20 days for serving a preliminary notice run from the date the claimant:

a.Records its claim of lien with the county recorder
b.First furnishes labor or material to the work
c.Receives its first progress payment on the job
d.Signs its subcontract with the direct contractor

解析

Civil Code §8204(a) requires the preliminary notice to be given not later than 20 days after the claimant has first furnished work on the work of improvement, and a claimant who gives it later may claim only for work provided within the 20 days before service and afterwards. (d) is the most attractive wrong answer, since a subcontract is often signed weeks before anyone mobilizes and the statute counts furnishing rather than signing. (c) reverses the purpose of the notice, which is served before there is any payment problem. (a) confuses the two instruments: the notice comes first, and §8410 makes it a condition of enforcing the lien that is recorded later.

法律依据: Civ. Code §8204(a)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈