Texas Master Plumber Exam — All Questions
60 questions
When a drainage stack is offset more than 45 degrees from vertical above the lowest branch, IPC §907 requires the offset to be vented:
- a.Only where the drainage stack is 6 inches in diameter or larger
- b.Where one branch interval or more is located above the offset
- c.Where five or more branch intervals are located above the offset✓
- d.Only where the building is a hospital or nursing home
Horizontal offsets of drainage stacks with five or more branch intervals above them are vented, by treating the upper section as a separate stack with a vent at its base and a vent for the lower section above the offset.IPC §907.1
A battery of eight floor-outlet water closets is to be circuit vented. Under IPC §914.4, a relief vent is required for the circuit-vented branch where:
- a.Four or more water closets connect to it and it receives discharge from upper branches✓
- b.The branch is made of cast iron and is longer than 20 feet in developed length
- c.Two or more lavatories connect to it and it serves a single story building
- d.The branch is larger than 3 inches in diameter and slopes at 1/8 inch per foot
A relief vent is needed for a circuit-vented horizontal branch serving four or more water closets that connects to a drainage stack receiving soil or waste discharge from upper horizontal branches.IPC §914.4
A vent header joins several vent stacks before one roof penetration. The header is sized, under IPC §906.1 and §904.5, by:
- a.The total fixture units vented and the developed length to the farthest vent stack base✓
- b.The diameter of the roofing flashing that is supplied for the vent terminal
- c.The diameter of the smallest vent stack that is connected to the header
- d.The number of roof penetrations that the header allows the installer to avoid
Vent headers are sized like vent stacks, using the sum of the drainage fixture units of all stacks connected and the developed length from the farthest stack base to the open air.IPC §§904.5, 906.1
Under IPC Chapter 13, piping that distributes on-site collected rainwater or reclaimed water for flushing must be:
- a.Installed in copper type K so that it can be told from potable pipe
- b.Cross-connected to the potable system through a single gate valve
- c.Kept separate from the potable system and identified as non-potable✓
- d.Left unmarked, so that occupants are not alarmed by warning labels
Non-potable water systems are separate from potable piping, identified by colour (purple for reclaimed water) and signage at outlets, and any potable makeup is protected by an air gap or approved backflow preventer.IPC §§1301.3, 608.8
Under IPC §305.3, a sleeve for a pipe passing through a foundation wall must be:
- a.The same size as the pipe passing through it
- b.Two pipe sizes larger than the pipe passing through it✓
- c.At least 12 inches larger than the pipe passing through it
- d.One half size smaller than the pipe hub
A relieving arch or a pipe sleeve built into the wall protects the pipe from settlement; the sleeve is two pipe sizes greater than the pipe, and the annular space is sealed.IPC §305.3
In a multi-story building, vertical cast-iron drainage stacks must be supported, under IPC §308.5, at:
- a.The base only, with a concrete pier under the lowest hub
- b.The base and each floor, not exceeding 15 feet✓
- c.The roof only, with a riser clamp
- d.Every third floor, not exceeding 45 feet
Vertical cast-iron pipe is supported at maximum intervals of 15 feet, which in practice means the base and each story; the base of the stack carries the weight during a water test.IPC §308.5; §308.9
Under IPC §312.3, an air test of a metal drainage and vent system is made at a pressure of:
- a.100 psi (200 inches of mercury), held for at least 24 hours
- b.50 psi (100 inches of mercury), held for at least 2 hours
- c.1/2 psi (1 inch of mercury), held for at least 5 minutes
- d.5 psi (10 inches of mercury), held for at least 15 minutes✓
The drainage and vent air test is 5 psi or 10 inches of mercury for 15 minutes with no added air. Plastic piping is not air tested.IPC §312.3
The final test of a completed drainage system with fixtures set, where the code official requires it under IPC §312.4, uses:
- a.Potable water, at the working pressure of the water main
- b.Smoke or peppermint, at a pressure equal to 1 inch of water column✓
- c.Compressed air, at a pressure equal to 50 psi on a gauge
- d.Nitrogen, at a pressure equal to 150 psi on a gauge
The final test fills the traps and introduces smoke under a pressure of 1 inch of water column for 15 minutes, or uses the odour of peppermint, to show leaks at fixture connections.IPC §312.4
Under IPC §301.6, plumbing systems may not be located in an elevator shaft or elevator equipment room, EXCEPT:
- a.Floor drains, sumps and sump pumps at the base of the shaft that are indirectly connected✓
- b.Water service piping, where it is insulated against condensation
- c.Roof conductors, where they are made of cast iron with caulked joints and are fully insulated
- d.Water closets and lavatories provided for the use of elevator mechanics
Plumbing is kept out of elevator shafts and machine rooms, apart from floor drains, sumps and sump pumps at the base of the shaft, provided they are indirectly connected to the plumbing system.IPC §301.6
Under IPC §314.2.1, condensate from an air handler in a commercial building may NOT be discharged:
- a.To an approved indirect waste receptor such as a floor sink
- b.To a properly trapped tailpiece on a lavatory in the building
- c.Into a street, alley or other area where it would cause a nuisance✓
- d.To an approved location outdoors, away from walkways
Condensate is conveyed to an approved place of disposal and does not discharge into a street, alley or other area where it would create a nuisance.IPC §314.2.1