Seguros y GravámenesPregunta 1568 de 1605
A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
a.Only for materials delivered after Day 60
b.For nothing at all
c.For the entire delivery history from Day 1
d.Within the 20 days before service (from about Day 20) and thereafter, but not for the earliest deliveries
Explicación
Civil Code §8204 limits a late preliminary notice's reach to work furnished within 20 days before the notice was served, plus everything after. Deliveries made more than 20 days before service (the earliest ones) fall outside the protected window.
Referencia Legal: Civ. Code §8204Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- An owner asks the contractor to provide a certificate of insurance naming the owner as additional insured. For the owner to actually have that status, the certificate must be accompanied by, or reflect:
- A stop payment notice, unlike a mechanics lien, does NOT need to be:
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)