On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
a.The claimant may still lien within 60 days
b.The claimant loses its mechanics lien right for that project (though other remedies like bond/stop-notice claims may remain)
c.The claimant's license is suspended
d.The deadline resets to 90 days
Explicación
Once a notice of completion is recorded, Civil Code §8414 gives non-direct claimants only 30 days. Missing it forfeits the mechanics lien remedy, although the claimant may still pursue a payment bond claim, stop payment notice (if timely), or breach-of-contract action.
Referencia Legal: Civ. Code §8414Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
- A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- A general contractor's CGL policy typically will NOT respond to which claim?
- A claim on a private-project payment bond generally requires the claimant to have:
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)