On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:

a.The claimant may still record within 60 days, as the direct contractor may
b.The claimant loses the mechanics lien, but other remedies may survive
c.The claimant may record within 90 days from actual completion instead
d.The claimant has 90 days from recording to file suit on the lien

Explicación

Civil Code §8414 gives a claimant other than the direct contractor 30 days after a recorded notice of completion; miss it and the lien remedy is gone, though a payment bond claim, a timely stop payment notice, or a plain breach-of-contract action may remain. (a) borrows the direct contractor's 60-day period under §8412, which is not available to lower-tier claimants. (c) is the no-notice rule the recording displaced. (d) states the §8460 deadline for suing on a lien already recorded, which never revives a lien that was recorded too late.

Referencia Legal: Civil Code §8414 / §8460

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar