On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:

a.The claimant may still lien within 60 days
b.The claimant loses its mechanics lien right for that project (though other remedies like bond/stop-notice claims may remain)
c.The claimant's license is suspended
d.The deadline resets to 90 days

Explicación

Once a notice of completion is recorded, Civil Code §8414 gives non-direct claimants only 30 days. Missing it forfeits the mechanics lien remedy, although the claimant may still pursue a payment bond claim, stop payment notice (if timely), or breach-of-contract action.

Referencia Legal: Civ. Code §8414

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar