Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?

a.Certificate of insurance
b.Mechanics lien
c.Stop payment notice
d.Payment bond claim

Explicación

A mechanics lien ultimately requires a foreclosure action against the owner's real property to collect, making it more cumbersome than a stop payment notice (reaching funds) or a payment bond claim (reaching a surety). Claimants often pursue funds or bonds first.