Seguros y GravámenesPregunta 1572 de 1605

A claim on a private-project payment bond generally requires the claimant to have:

a.Posted a 125% bond
b.Given the preliminary notice required for lien rights (unless excused), because bond rights parallel lien rights
c.Recorded a mechanics lien first
d.Obtained a court judgment first

Explicación

Under Civil Code §8600 et seq., a claimant's right to recover on a private-project payment bond generally depends on having given the preliminary notice required to preserve lien rights (unless excused, e.g., laborers). The bond claim parallels the lien claim's notice conditions.

Referencia Legal: Civ. Code §8600