Seguros y GravámenesPregunta 1572 de 1632

A claim on a private-project payment bond generally requires the claimant to have:

a.Posted a bond of 125 percent of the claim before making it
b.Given the preliminary notice lien rights require, unless excused
c.Recorded a mechanics lien against the property before claiming
d.Obtained a judgment against the direct contractor before claiming

Explicación

Under Civil Code §8600 et seq. the right to recover on a private-work payment bond tracks the notice conditions for a mechanics lien, so a claimant who had to give a preliminary notice must have given it — laborers and others excused from notice are excused here too. (a) imports the §8532 bond that accompanies a stop payment notice to a lender. (c) treats the remedies as sequential when they are alternative; a claimant may go against the bond without ever recording. (d) would make the bond useless, since its value is being payable without first litigating to judgment.

Referencia Legal: Civil Code §8600 et seq.

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar