Seguros y GravámenesPregunta 1572 de 1605
A claim on a private-project payment bond generally requires the claimant to have:
a.Posted a 125% bond
b.Given the preliminary notice required for lien rights (unless excused), because bond rights parallel lien rights
c.Recorded a mechanics lien first
d.Obtained a court judgment first
Explicación
Under Civil Code §8600 et seq., a claimant's right to recover on a private-project payment bond generally depends on having given the preliminary notice required to preserve lien rights (unless excused, e.g., laborers). The bond claim parallels the lien claim's notice conditions.
Referencia Legal: Civ. Code §8600Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
- A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
- The '$25,000' figure most commonly associated with California contractor licensing refers to the:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)