Obras PúblicasPregunta 1595 de 1605

Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:

a.Payment of prevailing wages
b.The use of any subcontractors
c.'Bid shopping' and 'bid peddling' after the contract is awarded
d.DIR registration

Explicación

The Subletting and Subcontracting Fair Practices Act (Public Contract Code §4100 et seq.) requires listing subcontractors performing more than one-half of one percent of the bid, to curb bid shopping (the prime pressuring listed subs for lower prices after award) and bid peddling. Substituting a listed sub requires following statutory procedures.

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar