Seguros y GravámenesPregunta 1538 de 1632
To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
a.Assignment of the lien to the construction lender holding the loan
b.Extension of credit, extending time to sue up to a year
c.Amendment increasing the lien to include interest accruing meanwhile
d.Acknowledgement of debt, which restarts the 90 days from signing
Explicación
Civil Code §8460 requires an action to enforce a lien within 90 days after recording, unless a notice of credit is recorded extending the time — and in no event may the action be brought more than one year after recording. (a) transfers the claim without touching the deadline; an assignee inherits the same clock. (c) confuses the amount with the time limit, and inflating a lien invites the §8422 overstatement problem. (d) imports a debt-acknowledgement rule from the statute of limitations, which does not restart the mechanics lien deadline.
Referencia Legal: Civil Code §8460Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
- 'Completed operations' coverage under a CGL policy is important to contractors because it covers:
- A sole-owner contractor holding only a Class B license, with no employees, wants to avoid carrying workers' compensation. Under B&P §7125 as it reads until January 1, 2028, the contractor may:
- Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?
- The 125% bond required to accompany a stop payment notice served on a construction LENDER exists to:
- Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?
Última revisión: · proceso editorial
Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)