Seguros y GravámenesPregunta 1541 de 1605
Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?
a.The subcontractor
b.The material supplier
c.The surety company
d.The project owner
Explicación
On a performance bond, the obligee is the party protected by the guarantee of completion — typically the project owner. The contractor is the principal and the bonding company is the surety. Subs and suppliers are protected instead by the payment bond.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
- Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?
- The 125% bond required to accompany a stop payment notice served on a construction LENDER exists to:
- The recorded mechanics lien must be served on the owner within what time relative to recording, along with the Notice of Mechanics Lien?
- A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
- California Civil Code §2782 generally makes VOID a construction contract provision that requires one party to indemnify another for the latter's:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)