Seguros y GravámenesPregunta 1473 de 1632

A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?

a.On every subcontractor and supplier working under the prime contract
b.On the owner, within 20 days, to preserve any lien right
c.On no one, because a direct contract dispenses with all notice
d.On the construction lender only, if the project has one

Explicación

Civil Code §8200(e) excuses a direct contractor from serving the owner — the contract itself gives the owner notice — but the direct contractor must still give the preliminary notice to a construction lender to preserve rights against the construction funds. (a) inverts the flow: notice runs up the chain toward the people who control the money, not down it. (b) applies the general rule without reading the exception, and is the trap for anyone who memorised '20 days' alone. (c) over-reads the exception, which covers only the owner and not the lender.

Referencia Legal: Civil Code §8200(e)

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar