Seguros y GravámenesPregunta 1472 de 1632

Which claimant is generally NOT required to serve a preliminary notice to preserve a mechanics lien?

a.A material supplier selling to a subcontractor
b.A sub-subcontractor under a subcontractor
c.An equipment lessor renting to a subcontractor
d.A laborer performing the work of the job for wages

Explicación

Civil Code §8200(e)(1) excuses a laborer from giving preliminary notice, and §8200(e)(2) excuses a claimant with a direct contractual relationship with the owner from notifying anyone but the construction lender. §8024 defines laborer as a person who, acting as an employee, performs labor on or bestows skill on a work of improvement, and extends the term to a fund owed part of that compensation. (a), (b) and (c) all lack an owner contract, so each must serve the owner, the direct contractor, and the lender within the §8204(a) 20 days — and an equipment lessor is the one people most often assume is exempt, when §8400(d) gives it a lien right on exactly the same conditions as anyone else.

Referencia Legal: Civ. Code §8200(e) / §8024

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar