Seguros y GravámenesPregunta 1469 de 1605

After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:

a.60 days
b.90 days
c.6 months
d.30 days

Explicación

Civil Code §8414 gives the direct contractor 60 days after recording of a notice of completion or cessation, while all other claimants get 30 days. If no such notice is recorded, all claimants have 90 days from completion under §8412.

Referencia Legal: Civ. Code §8414