Seguros y GravámenesPregunta 1469 de 1632
After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
a.60 days
b.90 days
c.6 months
d.30 days
Explicación
Civil Code §8414 gives the direct contractor 60 days after recording of a notice of completion or cessation, while all other claimants get 30 days. If no such notice is recorded, all claimants have 90 days from completion under §8412.
Referencia Legal: Civ. Code §8414Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- An unpaid framing subcontractor furnished labor and materials to a private remodel. Who is entitled to record a mechanics lien?
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- A preliminary notice must be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
- Which claimant is generally NOT required to serve a preliminary notice to preserve a mechanics lien?
Última revisión: · proceso editorial
Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)