Seguros y GravámenesPregunta 1467 de 1605
On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
a.Within 120 days after completion
b.Within 90 days after completion
c.Within 30 days after completion
d.Within 60 days after completion
Explicación
Civil Code §8412 gives a direct contractor 90 days after completion of the work of improvement to record a mechanics lien when no notice of completion or cessation has been recorded. The shorter deadlines apply only after such a notice is recorded.
Referencia Legal: Civ. Code §8412Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Un propietario tiene un fallo de $40,000 contra un contratista licenciado por trabajo incompleto en la residencia familiar. El bono de licencia de $25,000 del contratista también está siendo perseguido por un instalador de estructuras no pagado (reclamo salarial de $8,000) y por un propietario comercial no residencial (daños de $30,000). Bajo el esquema de prioridad del §7071.11, el propietario puede esperar aproximadamente:
- La póliza de responsabilidad civil general (CGL) de un subcontratista proporciona el estatus de 'asegurado adicional' al contratista principal por el trabajo negligente del subcontratista. Si un tercero se lesiona y demanda tanto al sub como al principal, conforme a la ley de California:
- A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)