Seguros y GravámenesPregunta 1467 de 1605

On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?

a.Within 120 days after completion
b.Within 90 days after completion
c.Within 30 days after completion
d.Within 60 days after completion

Explicación

Civil Code §8412 gives a direct contractor 90 days after completion of the work of improvement to record a mechanics lien when no notice of completion or cessation has been recorded. The shorter deadlines apply only after such a notice is recorded.

Referencia Legal: Civ. Code §8412