Seguros y GravámenesPregunta 1466 de 1605

A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?

a.Only suppliers who delivered material directly to the owner
b.Any creditor of the contractor, whether or not they worked on the project
c.Only the direct (prime) contractor who signed the contract with the owner
d.Any person who, at the owner's request or the request of a person acting on the owner's behalf, provided labor, services, equipment, or material for a work of improvement

Explicación

Under Civil Code §8400, a person who provides work authorized for a work of improvement — including direct contractors, subcontractors, material suppliers, equipment lessors, and laborers — has a mechanics lien right. The framing sub qualifies. Mere creditors of the contractor who did not contribute to the improvement have no lien.

Referencia Legal: Civ. Code §8400

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar