An unpaid framing subcontractor furnished labor and materials to a private remodel. Who is entitled to record a mechanics lien?
Explicación
Civil Code §8400 gives a lien right to a person that provides work authorized for a work of improvement, and lists the direct contractor, subcontractor, material supplier, equipment lessor, laborer, and design professional; §8404 defines authorized work as work requested or agreed to by the owner, or authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of part of the work. The framing subcontractor is squarely inside that. (b) is the limit that matters: a creditor who contributed nothing to the improvement, such as the contractor's landlord or lender, has no lien. (a) and (c) shrink the class to a single tier, which would leave every subcontractor and supplier without the remedy the chapter was written for.
Referencia Legal: Civ. Code §8400 / §8404Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- Un propietario quiere eliminar un gravamen mecánico de $60,000 registrado contra la propiedad para poder venderla o refinanciarla. Conforme al Civil Code §8424, el propietario puede obtener una liberación del gravamen registrando un bono de liberación de gravamen por la cantidad de:
- Los reclamos contra la fianza de licencia de $25,000 de un contratista suman mucho más de $25,000: un propietario residencial reclama $40,000, un carpintero de estructura impago reclama $8,000 en salarios y un propietario comercial reclama $30,000. Conforme al Bus. & Prof. Code §7071.11, ¿cómo se distribuye la fianza?
- La póliza de responsabilidad civil general (CGL) de un subcontratista proporciona el estatus de 'asegurado adicional' al contratista principal por el trabajo negligente del subcontratista. Si un tercero se lesiona y demanda tanto al sub como al principal, conforme a la ley de California:
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?