After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?

a.90 days after recording of the notice of completion
b.60 days after recording of the notice of completion
c.30 days after recording of the notice of completion
d.10 days after recording of the notice of completion

Explicación

Under Civil Code §8414, once a notice of completion (or cessation) is recorded, a claimant other than the direct contractor must record its lien within 30 days. The direct contractor gets 60 days after that notice. Absent any such notice, everyone has 90 days after completion.

Referencia Legal: Civ. Code §8414

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar