After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
a.90 days after recording of the notice of completion
b.60 days after recording of the notice of completion
c.30 days after recording of the notice of completion
d.10 days after recording of the notice of completion
Explicación
Under Civil Code §8414, once a notice of completion (or cessation) is recorded, a claimant other than the direct contractor must record its lien within 30 days. The direct contractor gets 60 days after that notice. Absent any such notice, everyone has 90 days after completion.
Referencia Legal: Civ. Code §8414Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- La póliza de responsabilidad civil general (CGL) de un subcontratista proporciona el estatus de 'asegurado adicional' al contratista principal por el trabajo negligente del subcontratista. Si un tercero se lesiona y demanda tanto al sub como al principal, conforme a la ley de California:
- A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)