Seguros y GravámenesPregunta 1471 de 1605

On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?

a.The owner (or reputed owner), the direct contractor, and the construction lender (if any)
b.The direct (prime) contractor only
c.The construction lender only
d.The owner only

Explicación

Civil Code §8200 requires a claimant without a direct contract with the owner to serve the preliminary notice on the owner (or reputed owner), the direct contractor, and the construction lender, if any. Missing a required recipient jeopardizes lien and stop payment notice rights.

Referencia Legal: Civ. Code §8200

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar