Which of these must a valid recorded mechanics lien contain?
Explicación
Civil Code §8416(a) requires a written statement, signed and verified by the claimant, containing the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant, a description of the site sufficient for identification, the claimant's address, and a proof of service affidavit; the statutory Notice of Mechanics Lien must be served with it. §8422 forgives erroneous information about the demand, the credits, the work, or the site unless the court finds the claimant intended to defraud, or a party without actual knowledge was misled to its prejudice. The other three answers are records no lien requires and that do nothing to identify the claim.
Referencia Legal: Civ. Code §8416(a) / §8422Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- The primary function of a 'certificate of insurance' in the contracting process is to allow one party to:
- Under California's workers' compensation system, an employee injured on the job generally receives benefits:
- A contractor's umbrella or excess liability policy is designed to:
- A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
- The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
- On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the: