Which of these must a valid recorded mechanics lien contain?

a.The claimant's demand, after just credits and offsets
b.A copy of the claimant's workers' compensation certificate
c.The owner's construction loan and account numbers
d.The claimant's profit margin on the contract

Explicación

Civil Code §8416(a) requires a written statement, signed and verified by the claimant, containing the claimant's demand after deducting all just credits and offsets, the name of the owner or reputed owner if known, a general statement of the kind of work furnished, the name of the person who employed the claimant, a description of the site sufficient for identification, the claimant's address, and a proof of service affidavit; the statutory Notice of Mechanics Lien must be served with it. §8422 forgives erroneous information about the demand, the credits, the work, or the site unless the court finds the claimant intended to defraud, or a party without actual knowledge was misled to its prejudice. The other three answers are records no lien requires and that do nothing to identify the claim.

Referencia Legal: Civ. Code §8416(a) / §8422

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar