Seguros y GravámenesPregunta 1555 de 1605

The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:

a.Assert a bonded stop payment notice against undisbursed construction loan funds held by the lender
b.Foreclose on the lender's office
c.Become an additional insured
d.Collect workers' compensation from the lender

Explicación

Serving the construction lender preserves the claimant's ability to serve a bonded stop payment notice reaching undisbursed loan funds. Without notifying the lender, that fund-based remedy against loan proceeds is jeopardized.

Referencia Legal: Civ. Code §8410