Seguros y GravámenesPregunta 1556 de 1605
On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
a.Notice of non-responsibility
b.Builder's risk policy
c.Contractor's payment bond (and stop payment notice against public funds)
d.Owner's homeowner policy
Explicación
Public property cannot be liened, so on public works the payment bond (required under the Little Miller Act framework) and stop payment notices against public funds are the primary payment protections for unpaid subs and suppliers.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Which of the following must a valid recorded mechanics lien include?
- A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
- The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
- After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)