Contratos y EjecuciónPregunta 700 de 1605
A home improvement contract states the project 'will start sometime soon and finish when done.' What is the defect?
a.It fails to state the approximate start and completion dates required by law
b.Nothing; approximate dates are optional
c.Dates are only required for contracts over $50,000
d.Only the start date is required, not completion
Explicación
B&P §7159 requires the contract to include the approximate dates when work will begin and when it will be substantially completed. Vague language fails this requirement.
Referencia Legal: B&P §7159(c)Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A 72-year-old homeowner signs a home improvement contract. How many business days does this senior buyer have to cancel?
- A contractor structures a home improvement contract so that each progress payment is due 'as work proceeds.' Under §7159, each progress payment must:
- Which document, warning homeowners that unpaid subcontractors and suppliers may place a claim against their home, must be included in a home improvement contract?
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
- After a home improvement contract is signed, when must the contractor give the homeowner a copy?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)