Contratos y EjecuciónPregunta 702 de 1632

A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:

a.Acceptable if filled in later that day
b.A prohibited act and grounds for disciplinary action
c.Allowed if the homeowner initials each blank
d.Allowed for repeat customers

Explicación

B&P §7161 makes it a prohibited act (and cause for discipline) to cause a buyer to sign a contract containing blank spaces to be filled in after signing.

Referencia Legal: B&P §7161