Contratos y EjecuciónPregunta 702 de 1605

A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:

a.Acceptable if filled in later that day
b.A prohibited act and grounds for disciplinary action
c.Allowed if the homeowner initials each blank
d.Allowed for repeat customers

Explicación

B&P §7161 makes it a prohibited act (and cause for discipline) to cause a buyer to sign a contract containing blank spaces to be filled in after signing.

Referencia Legal: B&P §7161

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar