Contratos y EjecuciónPregunta 699 de 1605
Which document, warning homeowners that unpaid subcontractors and suppliers may place a claim against their home, must be included in a home improvement contract?
a.A Notice of Completion
b.A Notice of Non-Responsibility
c.The Mechanics Lien Warning
d.A Preliminary Bond Notice
Explicación
B&P §7159 requires a home improvement contract to contain a Mechanics Lien Warning, informing the owner that those who supply labor or materials and are not paid may record a lien against the property.
Referencia Legal: B&P §7159(c)Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- After signing a home improvement contract at their kitchen table, a homeowner changes their mind. How many business days does the buyer generally have to cancel the contract?
- A 72-year-old homeowner signs a home improvement contract. How many business days does this senior buyer have to cancel?
- A contractor structures a home improvement contract so that each progress payment is due 'as work proceeds.' Under §7159, each progress payment must:
- A home improvement contract states the project 'will start sometime soon and finish when done.' What is the defect?
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)