保险与留置权第 1500 / 1605 题
A material supplier who furnishes materials to a subcontractor (not to the owner directly) preserves its mechanics lien rights by serving a preliminary notice on:
a.Only the subcontractor it dealt with
b.Only the owner
c.The owner, the direct contractor, and the construction lender (if any)
d.The CSLB
解析
Because the supplier has no direct contract with the owner, Civil Code §8200 requires service of the preliminary notice on the owner, the direct contractor, and the construction lender (if any). Serving only the subcontractor it dealt with is insufficient.
法律依据: Civ. Code §8410免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following is the BEST reason a general contractor requires subcontractors to name it as an additional insured and provide certificates of insurance?
- If a contractor illegally fails to carry required workers' compensation insurance and an employee is injured, the employee may:
- What is a direct consequence for a licensed contractor whose required workers' compensation insurance lapses?
- A 'performance bond' on a construction project primarily guarantees to the obligee that:
- Which of the following is generally NOT covered by a standard Commercial General Liability policy?
- Commercial auto insurance for a contractor is primarily intended to cover: