Browse all questions

The figures these questions turn on, laid out by section on dense colour pages you can print: CSLB Law & Business cheat sheet PDF — $9.99 →

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Every question with its answer and explanation — study by topic or all at once.

Business Finances

245 questions
101. Instead of filing a contractor's license bond, a licensee may deposit cash or equivalent securities with the State Treasurer under Bus. & Prof. Code §7071.12. To replace the $25,000 license bond entirely with cash, the licensee must deposit:
a.$5,000 in cash, at a 5:1 ratio to the bond face
b.The full $25,000 with the State Treasurer✓
c.$10,000 in cash combined with a $15,000 bond
d.$25,000 in an interest-bearing bank escrow account

B&P §7071.12 lets a licensee deposit cash, a cashier's check or specified securities in the full amount of the bond it replaces, and the deposit goes to the State Treasurer, where it answers claims on the same terms as a surety bond and is distributed pro rata under §7071.11(a) if it is not enough. There is no leverage ratio, so a $5,000 deposit secures nothing. There is no partial substitution either: cash and surety cannot be mixed to reach the figure. And a private bank escrow, however well insured, is not a deposit with the Treasurer.

Bus. & Prof. Code §7071.12; §7071.11(a)
102. A Responsible Managing Employee (RME) differs from a Responsible Managing Officer (RMO) in that an RME must:
a.Be related to one of the owners by blood or marriage
b.Own 10% or more of the shares of the licensed entity
c.Hold a Class A licence himself
d.Be a bona fide employee working at least 32 hours✓

An RMO is an officer of the licensed entity; an RME is a bona fide employee permanently employed by it, and 16 CCR §823 requires a qualifier who is not a bona fide owner to exercise direct supervision and control for at least 32 hours a week or 80 percent of the hours the business operates, whichever is less. Ownership of 10 percent or more is what relieves a qualifier of that hours test, so it describes the exemption rather than the RME. Family ties appear nowhere in §7068.1. And the licence class follows the work the entity is qualified for, not a personal credential the RME must hold.

B&P §7068.1; 16 CCR §823
103. A general contractor classifies its on-site framer as an independent contractor and issues a 1099-NEC instead of a W-2. If the framer is later determined to be a W-2 employee under AB-5 and federal common-law tests, the general contractor will likely be liable for:
a.Back payroll taxes plus misclassification penalties✓
b.Nothing at all, if the worker signed an acknowledgment
c.Only the gap between the 1099 amount and the W-2 net
d.Only a $250 penalty for the information return

Misclassification stacks two kinds of liability. The tax side is federal income tax withholding and both FICA shares under IRC §3402 and §3111, FUTA under §3301, and California PIT, SDI and UI through the EDD, with the reduced rates of IRC §3509 available only if the failure was not wilful. The labour side is a Labor Code §226.8 penalty of $5,000 to $15,000 per wilful violation, or $10,000 to $25,000 where there is a pattern, plus wage-statement penalties under §226(e) and uninsured-employer exposure for workers' compensation. A signed acknowledgment changes nothing, because Labor Code §2775(a) disregards the label the parties use. And the information-return penalty is a rounding error beside the rest.

Labor Code §226.8; §2775(a); IRC §3509
104. On a private works contract entered into on or after January 1, 2026, how much retention may be withheld from each payment?
a.Whatever the contract says; private retention has no statutory ceiling
b.No more than 5 percent, with two narrow statutory exceptions✓
c.No more than 10 percent, the long-standing private works custom
d.No more than 5 percent, but only on public works

Civil Code §8811, added by SB 61 and operative for contracts entered into on or after January 1, 2026, caps retention on a private work of improvement at 5 percent — of each payment and of the contract price — at every tier: owner to direct contractor, direct contractor to subcontractor, and below (b). The two exceptions behind the word 'narrow' are a residential project that is not mixed use and does not exceed four stories, and a subcontractor that fails to furnish a performance and payment bond from an admitted surety after written notice given at or before bid time. The prevailing party in an action to enforce the section recovers attorney's fees. (a) states the law as it stood before 2026, when private retention really was a pure matter of contract. (c) is the 10 percent custom the statute was passed to end; it now survives only inside those two exceptions and on contracts signed before 2026. (d) has the right figure but the wrong scope — Public Contract Code §7201 has capped most state and local public works at 5 percent for years, and §8811 extends the same ceiling to private work.

Civil Code §8811; Public Contract Code §7201
105. Effective January 1, 2023, the California Contractor License Bond was increased to:
a.$25,000✓
b.$50,000
c.$15,000
d.$12,500

B&P §7071.6, as amended by SB 607, raised the contractor licence bond from $15,000 to $25,000 effective 1 January 2023, and the Bond of Qualifying Individual under §7071.9 rose to $25,000 with it; the LLC employee and worker bond under §7071.6.5 is $100,000. $15,000 and $12,500 are pre-2023 figures, and $12,500 was the amount before 2016. No class of licence carries a $50,000 bond.

Bus. & Prof. Code §7071.6 (SB 607, 2021)
106. When is a Bond of Qualifying Individual (BQI) required, separate from the standard $25,000 Contractor License Bond?
a.When the licensee employs more than 10 workers
b.When the licensee works in two CSLB classes at once
c.When the licensee self-insures its workers' comp
d.When the qualifier owns under 10% of the firm✓

B&P §7071.9 requires a separate $25,000 bond of qualifying individual whenever the RMO or RME is not a bona fide owner of at least 10 percent of the licensed entity, because a qualifier with no real stake has less at risk if supervision lapses, and the bond gives the public a second source of recovery. Headcount is irrelevant to §7071.9. Holding more than one classification changes the scope of work, not the bonding. And self-insuring workers' compensation is a separate Labor Code §3700 process with its own security requirements.

Bus. & Prof. Code §7071.9
107. A contractor's direct job costs are $8,000. He applies a 25% markup on cost. What is the total price he charges the customer?
a.$6,000
b.$10,666
c.$10,000✓
d.$8,250

Markup is calculated on cost. $8,000 x 25% = $2,000 markup. Price = $8,000 + $2,000 = $10,000. (Note: a 25% markup is NOT the same as a 25% margin; a 25% margin would produce a price of $8,000 / 0.75 = $10,666.)

108. A job costs $12,000 and is sold for $15,000. What is the gross PROFIT MARGIN (as a percentage of the selling price)?
a.20%✓
b.12.5%
c.25%
d.15%

Gross profit = $15,000 - $12,000 = $3,000. Margin is profit divided by SELLING price: $3,000 / $15,000 = 0.20 = 20%. (The markup, by contrast, would be $3,000 / $12,000 = 25%.)

109. A contractor wants a 40% gross margin on a job whose direct costs are $6,000. What selling price must he set?
a.$8,400
b.$9,000
c.$8,000
d.$10,000✓

For a target margin, divide cost by (1 - margin). Selling price = $6,000 / (1 - 0.40) = $6,000 / 0.60 = $10,000. Check: profit = $10,000 - $6,000 = $4,000, and $4,000 / $10,000 = 40% margin. Marking up 40% on cost ($8,400) would give only a 28.6% margin, a common and costly error.

110. A 50% markup on cost is equivalent to what gross profit margin?
a.40%
b.25%
c.50%
d.33.3%✓

Take cost = $100. A 50% markup adds $50, giving a price of $150. Margin = profit / price = $50 / $150 = 33.3%. Markup and margin are different: markup is on cost, margin is on price.

Want these explained in order? CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

111. A contractor's price is $20,000 and direct cost is $16,000. What is the markup percentage on cost?
a.16%
b.80%
c.20%
d.25%✓

Markup = profit / cost. Profit = $20,000 - $16,000 = $4,000. Markup = $4,000 / $16,000 = 0.25 = 25%. (The margin on price would be $4,000 / $20,000 = 20%.)

112. To achieve a 30% gross margin, what markup on cost must a contractor apply?
a.42.9%✓
b.70%
c.30%
d.23.1%

The markup that yields a given margin = margin / (1 - margin). Here 0.30 / 0.70 = 0.4286 = 42.9%. Check with cost $100: 42.9% markup gives price $142.90; margin = $42.90 / $142.90 = 30%.

113. A contractor buys materials for $2,000 and applies a 35% markup. What is the marked-up material price?
a.$2,700✓
b.$2,070
c.$2,350
d.$3,077

$2,000 x 35% = $700 markup. Price = $2,000 + $700 = $2,700. Markup is added to cost.

114. Which statement about markup and margin is correct?
a.Margin exceeds markup for the same dollar profit
b.Margin is figured on price, markup on cost✓
c.Markup is figured on the selling price
d.Markup and margin are the same percentage

Margin states profit as a percentage of the selling PRICE; markup states the same dollar profit as a percentage of COST. Because price is the larger base, margin is always the smaller percentage, which is why the first option has it backwards. The third option swaps the bases outright. The fourth would hold only if cost equalled price, which would mean no profit at all.

115. A job sells for $50,000 with a 20% gross margin. What are the direct job costs?
a.$10,000
b.$41,667
c.$40,000 markup base only
d.$40,000✓

Margin 20% means profit is 20% of the $50,000 price = $10,000. Costs = price - profit = $50,000 - $10,000 = $40,000.

116. A contractor applies a 100% markup on a $3,000 cost. What margin does that represent, and what is the price?
a.Price $6,000; margin 100%
b.Price $6,000; margin 33%
c.Price $6,000; margin 50%✓
d.Price $3,000; margin 50%

100% markup doubles cost: price = $3,000 + $3,000 = $6,000. Margin = profit / price = $3,000 / $6,000 = 50%. A 100% markup always equals a 50% margin.

117. A contractor's annual overhead is $120,000 and he expects $600,000 in direct job costs this year. What overhead rate should he add to each job's direct cost to recover overhead?
a.25%
b.12%
c.5%
d.20%✓

Overhead recovery rate = annual overhead / annual direct costs = $120,000 / $600,000 = 0.20 = 20%. He adds 20% of each job's direct cost to cover overhead, then adds profit on top.

118. Which of the following is an example of OVERHEAD (indirect cost) rather than a direct job cost?
a.A subcontractor's plumbing invoice for the project
b.Office rent and the bookkeeper's salary✓
c.Wages of a carpenter framing the house
d.Lumber delivered to the jobsite

Overhead consists of indirect costs that keep the business running but are not tied to one specific job, such as office rent, administrative salaries, insurance, and utilities. Materials, on-site labor, and subcontractors are direct costs charged to a particular job.

119. A contractor's job has $10,000 direct costs. He adds 15% for overhead and then 10% profit on the resulting subtotal. What is the final price?
a.$12,500
b.$11,650
c.$12,650✓
d.$12,750

Direct cost $10,000 + 15% overhead ($1,500) = $11,500 subtotal. Then 10% profit on $11,500 = $1,150. Final price = $11,500 + $1,150 = $12,650. Order matters: overhead first, then profit on the total.

120. Overhead costs are best described as:
a.Ongoing costs not chargeable to a job✓
b.Costs that rise and fall with each job's size
c.The materials and labour bought for one job
d.The money left over after every cost is paid

Overhead is the indirect, ongoing cost of running the business — rent, office wages, insurance, trucks, licences — which cannot be billed to any single job and must be recovered across all of them through markup. Costs that scale with the job are direct costs, and materials and labour for a job are the clearest example of direct cost. What is left after every cost is paid is net profit, which comes after overhead rather than being it.

121. A contractor completes $800,000 in revenue with $560,000 direct costs and $160,000 overhead. What is the net profit and net profit margin?
a.$240,000; 30%
b.$80,000; 10%✓
c.$80,000; 14.3%
d.$80,000; 12.5%

Net profit = revenue - direct costs - overhead = $800,000 - $560,000 - $160,000 = $80,000. Net profit margin = $80,000 / $800,000 = 10%.

122. If a contractor underestimates his overhead rate when bidding, the most likely result is:
a.Bids come in high and he wins fewer jobs
b.Jobs are underpriced and the company loses money✓
c.His income taxes fall along with the reported profit
d.Overhead is absorbed by his subcontractors

When the overhead rate built into the markup is too low, every bid is priced below the true cost of doing business: the job can show a profit on its own sheet while the company loses money once real overhead is paid. Bidding high is the result of the opposite error, over-recovering overhead. Lower taxes follow a lower profit but are a symptom, not the harm. And subcontractors price their own overhead into their own numbers; nothing shifts the general contractor's overhead onto them.

123. A contractor has fixed costs of $90,000 per year. His contribution margin (price minus variable cost) is 30% of revenue. What annual revenue does he need to break even?
a.$300,000✓
b.$27,000
c.$117,000
d.$270,000

Break-even revenue = fixed costs / contribution margin ratio = $90,000 / 0.30 = $300,000. At $300,000 revenue, the 30% contribution margin ($90,000) exactly covers fixed costs, leaving zero profit.

124. A contractor's fixed (overhead) costs are $60,000/year. Each job nets $2,000 of contribution margin. How many jobs must he complete to break even?
a.12 jobs
b.20 jobs
c.30 jobs✓
d.60 jobs

Break-even units = fixed costs / contribution margin per job = $60,000 / $2,000 = 30 jobs. Below 30 jobs he loses money; above 30 he earns profit.

125. The break-even point is best defined as the level of sales at which:
a.Gross revenue equals the year's overhead alone
b.Variable costs exactly equal the fixed costs
c.Total revenue equals total costs exactly✓
d.Profit per job hits its highest point

Break-even is the sales volume at which total revenue equals total costs, fixed and variable together, so the result is neither profit nor loss. Covering overhead alone is not break-even, because direct job costs still have to be paid. Variable costs equalling fixed costs is an arbitrary coincidence with no meaning for profit. Maximum profit is a different point entirely, and it lies well above break-even.

126. A contractor has $100,000 fixed costs and a contribution margin ratio of 25%. If he wants a $50,000 profit, what revenue is required?
a.$400,000
b.$200,000
c.$150,000
d.$600,000✓

Required revenue = (fixed costs + target profit) / contribution margin ratio = ($100,000 + $50,000) / 0.25 = $150,000 / 0.25 = $600,000.

127. If a contractor's fixed costs rise while his contribution margin ratio stays the same, the break-even point will:
a.Increase✓
b.Stay the same
c.Decrease
d.Become zero

Break-even revenue = fixed costs / contribution margin ratio. Raising the numerator (fixed costs) while holding the ratio constant increases the break-even sales volume: he must sell more just to cover the higher fixed costs.

128. A framing job needs 3,200 board feet of lumber at $0.85 per board foot, plus 40 labor hours at $45/hour. What is the estimated direct cost?
a.$4,520✓
b.$3,920
c.$4,840
d.$2,720

Materials are 3,200 x $0.85 = $2,720 and labour is 40 x $45 = $1,800, so the direct cost is $4,520. $3,920 comes from pricing the labour at $30 an hour instead of $45. $4,840 comes from reading the lumber at $0.95 a board foot. $2,720 is the materials alone, with the labour line left out of the estimate.

129. A contractor estimates a job at 120 labor hours. Actual hours worked were 150. By what percentage did labor hours exceed the estimate?
a.25%✓
b.15%
c.30%
d.20%

Overrun = (actual - estimate) / estimate = (150 - 120) / 120 = 30 / 120 = 0.25 = 25%. Job costing compares estimated to actual to reveal a 25% labor overrun.

130. The primary purpose of JOB COSTING is to:
a.Spread the overhead evenly over every job
b.Track real costs against the estimate✓
c.Determine the sales tax owed on the materials
d.Set an hourly price for the next job to bid

Job costing records the labour, material, subcontract and equipment cost actually incurred on each project and sets it beside the estimate, so the contractor learns which jobs made money and bids the next one better. Spreading overhead is what the overhead rate does, and it is an input to the bid rather than the purpose of job costing. Sales tax is computed from purchase invoices. And an hourly price for the next job is guesswork unless the job history behind it has been costed.

131. A concrete slab is 30 ft x 40 ft x 4 inches thick. How many cubic yards of concrete are needed? (1 cubic yard = 27 cubic feet)
a.44.4 cubic yards
b.12.3 cubic yards
c.48 cubic yards
d.14.8 cubic yards✓

Volume in cubic feet = 30 x 40 x (4/12) = 30 x 40 x 0.333 = 400 cubic feet. Convert to cubic yards: 400 / 27 = 14.8 cubic yards.

132. A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
a.$28.00
b.$36.40
c.$37.80✓
d.$42.00

Burden adds 35% to the base wage: $28 x 1.35 = $37.80 per hour. Estimators must use the fully burdened rate, not the base wage, or labor will be underestimated.

133. A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
a.12 gallons
b.14 gallons✓
c.7 gallons
d.13 gallons

One coat: 2,400 / 350 = 6.86, round up to 7 gallons. Two coats need 2 x 6.86 = 13.7, round up to 14 gallons. Always round up when buying whole cans.

134. A subcontractor bids $18,000. The general contractor adds a 12% markup on that subcontract. What is the marked-up amount billed to the owner for that scope?
a.$2,160
b.$20,160✓
c.$18,000
d.$19,440 markup only

Markup = $18,000 x 12% = $2,160. Amount billed = $18,000 + $2,160 = $20,160. The general marks up subcontracts to cover coordination, supervision, and risk.

135. A good estimate should include a contingency allowance primarily to:
a.Raise the contractor's profit margin
b.Fund the five percent retention the owner withholds
c.Absorb unforeseen conditions and bid error✓
d.Cover the change orders the owner later requests

A contingency is money set aside inside the estimate to absorb unforeseen site conditions and the normal imprecision of estimating, so a small surprise does not have to become a claim. It is not profit: spending it leaves the margin intact, while treating it as profit means pricing the risk twice. Retention is the owner's money withheld from payments - five percent on public works under Public Contract Code section 7201, and capped at five percent on private contracts entered into on or after 1 January 2026 by Civil Code section 8811 - so it is money not yet received rather than a cost to fund. And owner-requested changes are paid through change orders at agreed prices, which is why they sit outside the contingency.

Public Contract Code §7201; Civil Code §8811
136. Working capital is calculated as:
a.Total assets minus the total liabilities owed
b.Current assets minus current liabilities✓
c.Revenue minus all of the operating expenses
d.Cash on hand minus the accounts payable

Working capital is current assets minus current liabilities, the short-term money actually available to run the business. Total assets minus total liabilities is owner's equity, which measures net worth rather than liquidity. Revenue minus operating expenses is operating profit, a period result rather than a balance. And cash minus payables ignores receivables, inventory and the rest of the current accounts, so it understates what is on hand to work with.

137. A contractor has current assets of $150,000 and current liabilities of $90,000. What is his working capital?
a.$1,667
b.$60,000✓
c.$90,000
d.$240,000

Working capital = current assets - current liabilities = $150,000 - $90,000 = $60,000. This is the cash cushion available for short-term obligations.

138. Poor cash flow on a construction project is MOST often caused by:
a.Paying suppliers early to take their discount
b.Holding retention back from all the subcontractors
c.Billing the owner monthly rather than weekly
d.Paying labour and materials before billings land✓

The structural cause is timing: wages and material invoices fall due weeks before the owner pays a progress billing, and retention delays part of the receipt further still, so cash drains even on a profitable job. Taking an early-payment discount does consume cash, but it buys a return and is a choice rather than the cause. Monthly billing lengthens the gap and makes the problem worse, without being its origin. Withholding retention from subs conserves the contractor's cash rather than draining it.

139. Why can a contractor be profitable on paper yet still run out of cash?
a.Profit is earned over time, bills fall due now✓
b.Accrued revenue is recorded twice in the ledger
c.Depreciation takes cash from the bank each month
d.Retention is booked as a loss when it is withheld

Accrual accounting books revenue when it is earned, but wages, suppliers and taxes must be paid in cash immediately, and money sitting in receivables, retention and work in progress is not available to spend. Double-recording revenue would be an error, not a reason. Depreciation is the opposite case: it reduces book profit without any cash leaving the bank. And retention is recorded as a receivable, an asset still owed, which is precisely why profit can look healthy while the bank balance does not.

140. A contractor offers 2/10, net 30 terms and pays a $10,000 supplier invoice on day 8. How much does he pay?
a.$10,000
b.$9,980
c.$9,800✓
d.$9,000

2/10, net 30 means a 2% discount if paid within 10 days. $10,000 x 2% = $200 discount. Payment = $10,000 - $200 = $9,800. Taking early-payment discounts improves margins.

141. A cash flow projection primarily helps a contractor:
a.Foresee cash shortfalls in time to arrange credit✓
b.Set the overhead rate each bid should carry
c.Value the work in progress for the balance sheet
d.Compute the depreciation on owned equipment

A cash flow projection lays expected receipts against expected disbursements week by week, so a shortfall is visible before it arrives and a line of credit or a change in billing can be arranged in time. Markup comes from the overhead rate and the target margin, not from a cash schedule. Work in progress is valued from job-cost records against the contract amounts. Depreciation follows the asset's cost and schedule and is a tax and book calculation, with no cash timing in it at all.

142. The current ratio is calculated as:
a.Total liabilities over total owner equity
b.Cash on hand over annual sales revenue
c.Current assets over current liabilities✓
d.Net income for the year over the total assets

The current ratio is current assets over current liabilities, a measure of whether short-term obligations can be met; about 2:1 is comfortable and below 1:1 signals trouble. Liabilities over equity is the debt-to-equity ratio, which measures leverage rather than liquidity. Cash over sales is a turnover-style figure that ignores everything else owed within the year. Net income over total assets is return on assets, a profitability measure.

143. A contractor has current assets of $200,000 and current liabilities of $80,000. What is his current ratio?
a.1.6 to 1
b.2.5 to 1✓
c.3.0 to 1
d.0.4 to 1

Current ratio = $200,000 / $80,000 = 2.5, expressed as 2.5:1. This means he has $2.50 of current assets for every $1.00 of current liabilities, a healthy short-term position.

144. Which financial statement reports a company's assets, liabilities, and owner's equity at a single point in time?
a.The job cost report, by project
b.The cash flow report, by week
c.The balance sheet, as of one date✓
d.The income statement, over a period

The balance sheet is a snapshot at a single date showing assets, liabilities and owner's equity, and it obeys Assets = Liabilities + Owner's Equity. The income statement covers a span of time and reports revenue less expenses. The cash flow statement also covers a span, tracking money in and out rather than assets owned. A job cost report is internal and reports one project's costs against its estimate, not the company's financial position.

145. The fundamental accounting equation is:
a.Owner's Equity = Assets + Liabilities
b.Assets = Revenue - Expenses
c.Assets = Liabilities + Owner's Equity✓
d.Revenue = Assets + Liabilities

Assets = Liabilities + Owner's Equity is the foundation of the balance sheet. Everything the company owns is financed either by what it owes (liabilities) or by the owner's investment and retained earnings (equity).

146. A contractor's balance sheet shows total assets of $500,000 and total liabilities of $320,000. What is the owner's equity?
a.$820,000
b.$180,000✓
c.$500,000
d.$320,000

Owner's equity = total assets - total liabilities = $500,000 - $320,000 = $180,000. Equity is the owner's residual claim after all debts.

147. Which statement summarizes revenues and expenses over a PERIOD of time to show profit or loss?
a.The trial balance, as of any chosen date
b.The balance sheet, as of one moment
c.The income statement, for a span✓
d.The equity statement, over each period

The income statement, also called the profit and loss statement, reports revenue minus expenses over a month, quarter or year and ends in net profit or loss. The balance sheet is a point-in-time snapshot of assets, liabilities and equity. A trial balance is a working list of ledger balances used to check that debits equal credits, not a report of profit. The statement of owner's equity does cover a period, but it explains changes in equity rather than showing how the profit was earned.

148. A quick ratio (acid-test) differs from the current ratio because the quick ratio:
a.Includes long-term debt
b.Divides by revenue instead of liabilities
c.Adds back depreciation
d.Excludes inventory from current assets✓

The quick ratio removes inventory (and other less-liquid items) from current assets before dividing by current liabilities, giving a stricter measure of the ability to pay short-term debts with the most liquid assets. Construction inventory can be slow to convert to cash.

149. A contractor's current ratio is 0.8 to 1. This most likely indicates:
a.Liquidity is strong for a firm that is growing
b.The company owes almost no short-term debt
c.Current liabilities exceed current assets✓
d.Profits are high relative to the total assets

A current ratio of 0.8 to 1 means there are only 80 cents of current assets for every dollar of current liabilities, so the near-term bills exceed the near-term resources and lenders and sureties read it as a warning. A ratio below 1.0 is the definition of weak liquidity, not strong. A firm with no short-term debt would show a very high ratio, not a low one. And the current ratio says nothing about profit, which is measured on the income statement.

150. What is the required amount of the contractor's license bond (bond of contractor) in California?
a.$15,000
b.$100,000
c.$25,000✓
d.$12,500

Under Business & Professions Code §7071.6, an active contractor's license requires a bond of $25,000 (an amount increased from $15,000 effective January 1, 2023). The bond protects consumers and employees, not the contractor.

Business & Professions Code §7071.6
Report