Browse all questions

The figures these questions turn on, laid out by section on dense colour pages you can print: CSLB Law & Business cheat sheet PDF — $9.99 →

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Every question with its answer and explanation — study by topic or all at once.

Business Finances

245 questions
40. A contractor's quick (acid-test) view of liquidity differs from the current ratio mainly because the quick ratio:
a.Excludes inventory from current assets✓
b.Includes long-term debt in the calculation
c.Adds depreciation back to assets
d.Uses annual revenue instead of assets

The quick ratio measures the ability to pay short-term debts using the most liquid assets, so it excludes inventory because inventory may not convert to cash quickly. The current ratio includes all current assets.

41. A contractor borrows $30,000 at 6% simple annual interest and repays it in full after 3 years. What is the total amount repaid?
a.$30,000
b.$1,800
c.$5,400
d.$35,400✓

Simple interest = $30,000 × 0.06 × 3 = $5,400. Total repaid = principal + interest = $30,000 + $5,400 = $35,400.

42. A contractor's fixed monthly costs total $18,000 and variable costs run 60% of revenue. What monthly revenue is needed to break even?
a.$45,000✓
b.$30,000
c.$10,800
d.$18,000

Break-even revenue = Fixed Costs ÷ (1 − Variable Cost Ratio) = $18,000 ÷ (1 − 0.60) = $18,000 ÷ 0.40 = $45,000.

43. On a $150,000 contract, the owner withholds 5% retention from each progress payment. After all work is billed, how much money is being held as retention?
a.$1,500
b.$7,500✓
c.$15,000
d.$142,500

Retention = 5% x $150,000 = $7,500 (b), held by the owner until the project is accepted, which the contractor must plan for in its cash flow. Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026, and Public Contract Code §7201 sets the same ceiling on most public works. (c) $15,000 applies the 10% that was customary on private jobs before 2026. (d) $142,500 is the amount paid out, not the amount held. (a) $1,500 is 1%, a decimal slip.

44. Why does retention (retainage) create a cash-flow challenge for a contractor?
a.It raises the contractor's overhead rate
b.It must be paid over to the IRS each quarter
c.It is added to the contract price as a penalty
d.Costs are paid before the money arrives✓

Retention is money already earned but held back until the work is complete and accepted, while wages, materials and subcontractors still have to be paid on time, so the contractor funds the last slice of every job out of its own pocket. It does not change the overhead rate, which is computed from the company's own costs. It is not a tax and never goes to the IRS. And it is not added to the price: it is withheld from payments that are already part of the price, which is why Public Contract Code §7107 penalises a public entity that holds it too long.

Public Contract Code §7107; Civil Code §8812
45. Including a contingency line item in a project budget is intended to:
a.Replace the contractor's profit line in the budget
b.Avoid the payroll taxes on the job
c.Increase the retention the owner keeps
d.Reserve money for unforeseen costs✓

A contingency is a budgeted reserve for site conditions, small scope surprises and ordinary estimating error, and it is spent only when one of those arises; what is left belongs to the job's result. It is not profit, and treating it as profit means the risk has been priced once and collected twice. Payroll taxes are owed on wages whatever the budget says. And retention is set by the contract and withheld by the owner, so nothing in the contractor's own budget can change it.

46. Which of the following is a VARIABLE cost that rises and falls with the volume of construction work performed?
a.Concrete and lumber purchased for active jobs✓
b.Annual general liability insurance premium
c.Monthly office lease payment
d.The contractor's annual CSLB license renewal fee

Materials such as concrete and lumber are variable costs: the amount spent rises and falls directly with job volume, and each purchase is traceable to a specific job. The other three are classified as overhead because they are NOT chargeable to any single job. Note for practising contractors: a commercial general liability premium is typically rated on payroll or gross receipts and audited at the end of the policy year, so the amount you ultimately pay does move with volume — but it is still overhead for cost-classification purposes, because it cannot be assigned to one project. The exam tests the classification, not the rating method.

47. Job costing is BEST described as a system that:
a.Tracks and assigns costs to each individual project✓
b.Spreads all costs equally across every project in a year
c.Records only the company's overhead expenses
d.Replaces the need for an income statement

Job costing accumulates labor, materials, subcontractor, and other costs by individual project, letting the contractor compare actual costs to the estimate and judge each job's profitability.

48. Which of the following would be classified as a DIRECT cost on a specific project's job cost report?
a.The bookkeeper's salary at the main office
b.Electricity for the company's headquarters
c.Advertising for the contracting business
d.Wages of carpenters on that project✓

Direct costs are traceable to a specific project, such as the wages of workers on that job, its materials, and its subcontractors. Office salaries, headquarters utilities, and advertising are overhead (indirect).

49. A contractor's income statement for the year shows revenue of $800,000, job costs of $560,000, and overhead of $160,000. What is the net profit?
a.$240,000
b.$160,000
c.$640,000
d.$80,000✓

Net profit = Revenue − Job Costs − Overhead = $800,000 − $560,000 − $160,000 = $80,000.

Want these explained in order? CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

50. A contractor's net profit for the year is $60,000 on total revenue of $750,000. What is the net profit margin?
a.8%✓
b.12.5%
c.15%
d.80%

Net profit margin = Net Profit ÷ Revenue = $60,000 ÷ $750,000 = 0.08 = 8%.

51. The PRIMARY purpose of preparing a business budget for the upcoming year is to:
a.To satisfy a CSLB licensing requirement
b.To remove the need to file tax returns
c.To guarantee that no job will lose money
d.To plan revenue, expenses and cash✓

A budget projects the coming year's revenue and cost so the contractor can see when cash will be short, set targets for volume and margin, and compare actual results against the plan month by month. Nothing in the licence law requires one, which is why it is a management tool rather than a filing. It does not replace a tax return: the return reports what happened, the budget forecasts what should. And no plan can guarantee a job's result; the budget only makes the shortfall visible sooner.

52. A contractor projects $1,000,000 in revenue and budgets overhead at 18% of revenue. How much should be budgeted for overhead?
a.$18,000
b.$100,000
c.$180,000✓
d.$820,000

Budgeted overhead = $1,000,000 × 18% = $180,000. Comparing actual overhead to this budget helps the contractor control indirect costs.

53. A contractor compares the budget to actual results and finds materials cost $52,000 against a budgeted $45,000. This $7,000 difference is called a:
a.A favourable budget variance
b.A contingency being drawn down
c.The unfavourable variance✓
d.Net profit for the month here

The gap between a budgeted figure and the actual result is a budget variance, and spending $52,000 where $45,000 was planned is unfavourable because it takes $7,000 out of the planned profit. A favourable variance is the same measure with the sign the other way, where actual cost comes in under budget. Drawing down a contingency is how a budget absorbs such an overrun, not the name of the gap. And net profit is the bottom line of the whole period, not the difference on one line item.

54. Which financial statement specifically shows how cash moved into and out of the business during a period?
a.The job cost estimate, by trade
b.The balance sheet, at a set date
c.The income statement, for the whole period
d.The cash flow statement, for a period✓

The cash flow statement reports money in and money out across operating, investing and financing activities, which is why a profitable contractor's shortage of cash shows up there and nowhere else. The balance sheet gives position at one date and shows the cash balance without explaining how it moved. The income statement measures revenue and expense earned and incurred, which is not the same as received and paid. And a job cost estimate is a pre-construction working document, not a financial statement at all.

55. It is possible for a contractor to show a net profit on the income statement yet still be unable to pay its bills. This situation is best explained by:
a.Poor cash flow, since profit is not cash✓
b.An error in the contractor's CSLB licence
c.Having far too little overhead in the bids
d.Charging far too high a markup on jobs

Profit is an accrual result while bills are paid in cash, and money parked in receivables, retention and work in progress is earned but unavailable, so the bank can be empty while the income statement looks healthy. A licence error stops the contractor working; it does not create this pattern. Under-recovering overhead destroys profit, so the income statement would not show a profit at all. And too high a markup loses bids rather than cash.

56. A contractor's job is 30% complete. Total estimated job costs are $250,000 and the contract price is $320,000. Under the percentage-of-completion method, how much job cost should be recognized to date?
a.$96,000
b.$320,000
c.$75,000✓
d.$250,000

Cost recognized = Total Estimated Costs × Percentage Complete = $250,000 × 30% = $75,000. The matching revenue would be $320,000 × 30% = $96,000.

57. On a balance sheet, which of the following is classified as a CURRENT asset?
a.Accounts receivable due within 60 days✓
b.A construction crane owned by the company
c.The company's office building
d.A 5-year equipment loan

Current assets are expected to convert to cash within one year — for example, cash, accounts receivable, and inventory. A crane and a building are long-term assets; a 5-year loan is a long-term liability.

58. A contractor has current assets of $120,000 and current liabilities of $80,000. What is the current ratio?
a.1.5✓
b.0.67
c.2.0
d.40

Current ratio = Current Assets ÷ Current Liabilities = $120,000 ÷ $80,000 = 1.5. A ratio of 1.5 means the contractor has $1.50 of current assets for every $1.00 of current liabilities.

59. California's PACE (Property Assessed Clean Energy) program allows a property owner to finance energy-efficiency or water-conservation improvements and repay the cost through:
a.A reduction in the contractor's licence bond amount
b.A deduction from the contractor's payroll tax
c.An assessment on the owner's property tax bill✓
d.A grant that never has to be repaid at all

PACE financing is repaid as a contractual assessment placed on the property owner's annual property tax bill, which is why it runs with the land and why a PACE solicitor must be registered under Financial Code §22017. The contractor's licence bond secures compliance with the licence law and has nothing to do with the owner's financing. Payroll tax is an employer liability, not a source of project funds. And PACE is a loan repaid over years, so calling it a grant misses the whole point of the programme.

Streets & Highways Code §5898.20; Financial Code §22017
60. A contractor's job estimate includes $40,000 materials, $35,000 labor, and $25,000 subcontractors. The contractor adds 16% overhead and then 12% profit on the overhead-loaded cost. What is the bid price (rounded to the nearest dollar)?
a.$100,000
b.$116,000
c.$129,920✓
d.$112,000

Direct costs = $40,000 + $35,000 + $25,000 = $100,000. With overhead: $100,000 × 1.16 = $116,000. With profit: $116,000 × 1.12 = $129,920.

61. A contractor pays a worker $25 per hour for 45 hours in one week, with overtime at 1.5 times the regular rate for hours over 40. What are the gross wages for the week?
a.$1,125.00
b.$1,012.50
c.$1,687.50
d.$1,187.50✓

Regular pay = 40 × $25 = $1,000. Overtime = 5 × ($25 × 1.5) = 5 × $37.50 = $187.50. Gross wages = $1,000 + $187.50 = $1,187.50.

62. Beyond an employee's gross wages, a contractor must also budget for the employer's share of payroll taxes. This additional cost is commonly referred to as:
a.Retainage
b.Labor burden✓
c.Contingency
d.Gross margin

Labor burden is the added cost of employing a worker beyond base wages — including the employer's payroll taxes, workers' compensation insurance, and benefits. Estimators must add labor burden to bid jobs accurately.

63. A worker is paid a base wage of $30 per hour. With a labor burden of 35%, what is the fully burdened hourly cost the contractor should use for estimating?
a.$10.50
b.$40.50✓
c.$30.00
d.$45.00

Burdened cost = Base Wage × (1 + Burden Rate) = $30 × 1.35 = $40.50. Estimating with only the base wage would understate the true cost of labor.

64. A contractor wins a job for $300,000 and incurs total costs of $264,000. What is the profit margin on the selling price?
a.13.6%
b.10%
c.12%✓
d.36%

Profit = $300,000 − $264,000 = $36,000. Margin = Profit ÷ Selling Price = $36,000 ÷ $300,000 = 0.12 = 12%.

65. A contractor wants to keep a cash reserve equal to 2 months of fixed overhead. If monthly fixed overhead is $14,000, how large should the reserve be?
a.$7,000
b.$14,000
c.$16,000
d.$28,000✓

Cash reserve = 2 × Monthly Fixed Overhead = 2 × $14,000 = $28,000. Maintaining a reserve helps the contractor cover overhead during slow periods or payment delays.

66. Accounts payable on a contractor's balance sheet represents:
a.Money owed to suppliers and the subs✓
b.Money the customers owe to the contractor
c.Cash held in the company's own bank account
d.The owner's own investment into the business

Accounts payable is a current liability: what the contractor owes suppliers, subcontractors and other vendors for work and material already received. What customers owe the contractor is accounts receivable, an asset on the other side of the sheet. Cash is its own asset line and is separate from either. And the owner's investment is contributed capital inside equity, which is neither a receivable nor a payable.

67. A contractor finances a $24,000 piece of equipment with a 4-year loan at 7% simple annual interest. What is the total interest paid over the life of the loan?
a.$1,680
b.$6,720✓
c.$24,000
d.$30,720

Simple interest = Principal × Rate × Time = $24,000 × 0.07 × 4 = $6,720. The total amount repaid would be $24,000 + $6,720 = $30,720.

68. A contractor's progress payment application bills $80,000 of completed work. The owner withholds 5% retention. How much cash will the contractor actually receive on this payment?
a.$80,000
b.$4,000
c.$76,000✓
d.$84,000

Retention withheld = 5% x $80,000 = $4,000. Cash received = $80,000 - $4,000 = $76,000 (c); the $4,000 is collected later when retention is released. Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026. (a) $80,000 ignores the withholding. (b) $4,000 is the retention, not the payment. (d) $84,000 adds the retention rather than deducting it.

69. Which document collects an independent contractor's name, address, and taxpayer identification number so the payer can later issue a 1099-NEC?
a.Form W-9✓
b.Form W-2
c.Form W-4
d.Form 941

Form W-9 is completed by an independent contractor (payee) to provide their taxpayer identification number to the payer. The payer uses that information to prepare a 1099-NEC at year-end.

70. A contractor's overhead is the same each month whether it completes 2 jobs or 8 jobs. Therefore, the per-job share of overhead is LOWEST when the contractor:
a.Completes fewer jobs over the period
b.Raises its profit margin
c.Lowers its bid prices
d.Completes more jobs over the period✓

Fixed overhead is spread across all jobs done in a period. The more jobs completed, the smaller the overhead allocation each job must absorb, which is why steady work volume improves competitiveness.

71. A schedule of values that allocates more value to early line items than the work actually justifies is sometimes called "front-loading." From the owner's perspective, the risk of front-loading is that:
a.The job will be reported as ahead of schedule
b.The contractor is overpaid relative to work done✓
c.The owner will pay less retention than the debt
d.Overhead costs will be left out of the price

Front-loading shifts contract value into early line items so the contractor draws more cash than the completed work justifies, and the owner is left holding too little of the price against the work that remains - exactly the security retention is supposed to preserve. Option (a) names a real side effect and mistakes it for the risk: a front-loaded schedule of values does make the job report as further along than it is, because percent complete is computed from billed value, but the harm is the money, not the report. Retention is a percentage of each payment and does not fall because the line items were reshuffled. And overhead sits inside the line items either way.

72. A contractor reviews three completed jobs and finds Job A earned $12,000 profit on $100,000 revenue, Job B earned $9,000 on $90,000, and Job C earned $4,000 on $80,000. Which job had the HIGHEST profit margin?
a.All three were equal
b.Job C
c.Job A✓
d.Job B

Margin = Profit ÷ Revenue. Job A = $12,000 ÷ $100,000 = 12%; Job B = $9,000 ÷ $90,000 = 10%; Job C = $4,000 ÷ $80,000 = 5%. Job A has the highest margin.

73. A contractor that fails to make required quarterly estimated tax payments to the IRS during the year is most likely to face:
a.Automatic suspension of the CSLB licence
b.A reduction in the contractor's bonding limits
c.A requirement to switch to accrual accounting
d.An underpayment penalty on the annual return✓

IRC §6654 charges an addition to tax when too little was paid in through estimated instalments during the year, and the charge is computed quarter by quarter on the shortfall, so paying in full with the April return does not cure it. Licence status is a CSLB matter and does not turn on federal tax timing. Bonding limits are the surety's own credit decision. And the method of accounting is chosen under IRC §446 and changed only with IRS consent, never as a penalty.

IRC §6654
74. A contractor's fixed overhead is $9,000 per month and variable costs are 75% of revenue. If the contractor produces $30,000 of revenue in a month, what is the net result for that month?
a.A profit of $1,500
b.Break-even (zero)
c.A loss of $1,500✓
d.A profit of $7,500

Variable costs = 75% × $30,000 = $22,500. Total costs = $22,500 + $9,000 fixed = $31,500. Result = $30,000 − $31,500 = a $1,500 loss, because revenue is below the break-even point of $36,000.

75. A contractor purchases materials on 30-day terms with a 2% discount if paid within 10 days. On a $20,000 invoice, how much is saved by paying within 10 days?
a.$200
b.$400✓
c.$600
d.$2,000

Early-payment discount = 2% × $20,000 = $400. Taking supplier discounts when cash allows is a simple way to reduce material costs and improve job margins.

76. A contractor's job came in with actual costs of $88,000 against an estimate of $80,000, while the contract price stayed at $95,000. The MOST useful lesson from this job cost comparison is that:
a.The contractor should stop tracking job costs
b.The estimate ought to have been lower
c.The contract price was set far too high
d.The estimate was low, so review future bids✓

Actual cost of $88,000 against an $80,000 estimate is an $8,000 overrun, and the useful question is why the estimate missed — labour hours, material prices, a scope item left out — so the next bid is built on better numbers. The job still earned $7,000, so the price was not too high; a higher price might have lost the job altogether. A lower estimate would have widened the gap rather than closed it. And abandoning job costing removes the only record that made the overrun visible.

77. A contractor has current assets of $240,000 (including $60,000 in inventory and $20,000 in prepaid expenses) and current liabilities of $100,000. What is the quick (acid-test) ratio?
a.2.40
b.1.60✓
c.1.80
d.2.20

Quick ratio = (Current Assets − Inventory − Prepaid Expenses) ÷ Current Liabilities = ($240,000 − $60,000 − $20,000) ÷ $100,000 = $160,000 ÷ $100,000 = 1.60. The quick ratio is stricter than the current ratio because it removes assets that cannot be converted to cash quickly.

78. When is the quick ratio more meaningful than the current ratio for a construction company?
a.When the company carries no inventory at all
b.When judging long-term solvency over years
c.When current assets sit in slow stock✓
d.When the company is profitable and growing fast

The quick ratio strips inventory and other slow current assets out of the numerator, so it matters most when a contractor's current assets are heavy with stockpiled material or unbilled work in progress that cannot become cash in time to pay this month's bills. If there is no inventory or work in progress, the quick and current ratios converge and the distinction disappears. Long-term solvency is measured with debt-to-equity and coverage ratios instead. And profitable growth often makes the problem worse, because growth consumes cash.

79. A contractor has annual credit sales of $1,825,000 and an average accounts receivable balance of $250,000. What is the Days Sales Outstanding (DSO)?
a.50 days✓
b.37 days
c.60 days
d.73 days

DSO = (Average Accounts Receivable ÷ Annual Credit Sales) × 365 = ($250,000 ÷ $1,825,000) × 365 = 0.13699 × 365 ≈ 50 days. DSO measures how long it takes to collect from customers; a rising DSO indicates collection problems.

80. A contractor's annual cost of goods sold is $1,460,000, average accounts payable is $200,000, and average inventory turns are 36 days. What is the Days Payable Outstanding (DPO)?
a.25 days
b.36 days
c.40 days
d.50 days✓

DPO = (Average Accounts Payable ÷ Annual COGS) × 365 = ($200,000 ÷ $1,460,000) × 365 = 0.13699 × 365 = 50 days. A higher DPO means the contractor takes longer to pay suppliers, which can improve cash flow but risk supplier relationships.

81. A contractor has DSO of 55 days, days inventory outstanding (DIO) of 30 days, and DPO of 40 days. What is the cash conversion (working-capital) cycle?
a.35 days
b.45 days✓
c.65 days
d.125 days

Cash Conversion Cycle = DSO + DIO − DPO = 55 + 30 − 40 = 45 days. This is how long cash is tied up between paying suppliers and collecting from customers. Shorter cycles reduce the need for working capital.

82. A contract has a total contract price of $500,000 and an estimated total cost of $400,000. To date, the contractor has incurred $300,000 in actual cost and billed the owner $360,000. Using the cost-to-cost percentage-of-completion method, what is the percent complete and the revenue earned to date?
a.60% complete; $300,000 earned
b.72% complete; $360,000 earned
c.75% complete; $375,000 earned✓
d.80% complete; $400,000 earned

Percent Complete = Cost Incurred ÷ Estimated Total Cost = $300,000 ÷ $400,000 = 75%. Revenue Earned = 75% × $500,000 contract price = $375,000. Because billings ($360,000) are less than earned revenue ($375,000), the contract is under-billed by $15,000.

83. A contractor has earned $400,000 in revenue under percentage-of-completion accounting, but has billed the customer $450,000 to date. How is this $50,000 difference reported on the balance sheet?
a.A current liability, from over-billing✓
b.A current asset, as an under-billing
c.Deferred revenue, as a long-term item
d.A reduction of accounts receivable

Billing $450,000 against $400,000 of revenue earned means $50,000 has been invoiced for work not yet performed, so it is a current liability, usually captioned billings in excess of costs and estimated earnings. The mirror case, earning more than has been billed, is the current asset called costs and estimated earnings in excess of billings, and it is the wrong side here. The obligation is expected to be worked off within the contract, so it is not long-term. And receivables record what the customer owes, which the over-billing does not reduce.

ASC 606; ASC 340-40
84. Under current IRS rules, which form must a contractor file to report $3,600 paid to an unincorporated independent subcontractor for services performed during the tax year?
a.Form 1099-MISC, due February 28
b.Form 1099-NEC, due January 31✓
c.Form W-2, due January 31
d.Form 1096, due April 15

Nonemployee compensation is reported on Form 1099-NEC, due to both the recipient and the IRS by January 31 (b). Reporting kicks in once annual service payments reach the threshold, which is $2,000 for tax year 2026; $600 was the figure through tax year 2025, and $3,600 clears either line. (a) the 1099-MISC kept the February 28 paper deadline but lost nonemployee compensation in 2020 and now covers rents, royalties and other miscellaneous payments. (c) a W-2 is for employees only, though it shares the January 31 date. (d) Form 1096 is the paper transmittal summary that accompanies paper information returns; it is not the return itself and is not due April 15.

85. Under IRS rules, when does a contractor's payroll tax liability require deposits by electronic funds transfer (EFTPS) rather than by check?
a.Once the business employs more than ten people
b.Only when the contractor is an S corporation
c.When annual federal deposits top $200,000✓
d.Whenever the federal government pays it

26 CFR §31.6302-1(h) requires electronic deposit once a business made more than $200,000 in aggregate federal tax deposits in a prior determination year, and once the rule applies it keeps applying even if later deposits fall below the figure. Headcount is not the test, and a ten-employee shop may be far under the threshold. The entity type is irrelevant: the rule follows dollars deposited, not whether the payer is a corporation, an LLC or a proprietor. And being paid by the federal government affects how the contractor is paid, not how it deposits.

26 CFR §31.6302-1(h)
86. Under §530 of the Revenue Act of 1978 ("§530 safe harbor"), a contractor may continue treating workers as independent contractors for federal employment-tax purposes only if which of the following is true?
a.The workers each earn under $600 a year
b.The workers sign a waiver of employee status
c.The contractor pays them through a payroll firm
d.Reasonable basis, consistency and 1099s filed✓

Section 530 relief needs all three prongs together: a reasonable basis for treating the workers as contractors, such as judicial precedent, a prior audit or long-standing industry practice; substantive consistency, meaning the firm has never treated these or substantially similar workers as employees; and reporting consistency, meaning every required Form 1099 was actually filed. A pay threshold is not one of them, and the 1099-NEC threshold is $2,000 for tax year 2026 in any case. Workers cannot waive employee status by signing. And using a payroll service describes the mechanics of payment, not the basis for classification.

Revenue Act of 1978 §530
87. Under California AB 5, what must a hiring contractor demonstrate to classify a worker as an independent contractor under the "ABC test"?
a.Control, outside the usual business, and a trade✓
b.Only that the worker signed a 1099 form
c.That the worker brings his own tools
d.That the subcontractor holds a CSLB licence

The ABC test in Labor Code section 2775(b)(1) presumes a worker is an employee unless the hiring entity proves all three: (A) the worker is free from the control and direction of the hirer in performing the work; (B) the work is outside the usual course of the hirer's business; and (C) the worker is customarily engaged in an independently established trade of the same nature as the work performed. All three, not the best two. A 1099 is a tax form the hirer issues and proves nothing about the relationship. Bringing tools and setting hours is the old common-law control factor, which survives inside prong A but is not the test. And the CSLB licence is the most instructive wrong answer: it is a real requirement, but of section 2781 - the construction-subcontractor exception, which takes a relationship OUT of the ABC test altogether if the contractor shows a written subcontract, a licensed subcontractor working within its licence, a separate business location, authority to hire and fire, and five more conditions.

Labor Code §2775(b)(1); §2781(a)
88. California Form DE 542 must be filed by a contractor with the Employment Development Department (EDD) within how many days of paying or contracting with an independent contractor for $600 or more in services?
a.10 days
b.20 days✓
c.30 days
d.60 days

California requires businesses to file the DE 542 (Report of Independent Contractor(s)) with the EDD within 20 days of either making payments totaling $600 or more or entering a contract for $600 or more — whichever is earlier. This helps the state enforce child-support obligations.

89. What is the key difference between IRS Form 941 and Form 944 for payroll-tax reporting?
a.941 covers federal tax; 944 covers the state tax
b.941 is for S corporations; 944 for proprietors
c.941 is quarterly; 944 is annual for the small✓
d.941 is for employees; 944 for contractors

Form 941 is the quarterly federal employment tax return most employers file, and Form 944 is its annual counterpart for the smallest employers, available only when annual employment tax liability is about $1,000 or less and only after the IRS writes to say the employer may use it. Both are federal; state payroll reporting goes to the EDD on its own forms. Entity type does not decide which return is filed. And neither form reports payments to independent contractors, which go on a 1099-NEC.

26 CFR §31.6011(a)-1; §31.6011(a)-4
Report