Browse all questions
The figures these questions turn on, laid out by section on dense colour pages you can print: CSLB Law & Business cheat sheet PDF — $9.99 →
Every question with its answer and explanation — study by topic or all at once.
Business Finances
245 questionsPayback Period = Initial Investment ÷ Annual Net Cash Inflow = $50,000 ÷ $20,000 = 2.5 years. Payback ignores time value of money and post-payback cash flows; it is used as a quick liquidity-risk screen for capital expenditures.
Estimated total = $50,000 + $45,000 + $25,000 = $120,000. Actual total = $55,000 + $48,000 + $22,000 = $125,000. Variance = Actual − Estimated = $125,000 − $120,000 = $5,000 OVER budget, which is unfavorable. Labor and materials overruns more than offset the equipment savings.
FUTA is 6.0 percent on the first $7,000 of each worker's wages under IRC §3301, but an employer in a state that pays its SUI on time takes the 5.4 percent credit under §3302, leaving 0.6 percent, or $42 per worker per year. California's new-employer SUI rate is 3.4 percent on the same first $7,000, with experience-rated employers running roughly 1.5 to 6.2 percent — which is where the stray 1.5 and 6.2 figures in the other options come from. No California unemployment wage base is $14,000, and 6.0 percent is the FUTA rate before the credit, not after.
IRC §3301; IRC §3302; Unemp. Ins. Code §982IRC §6654(c)(2) sets an individual's estimated-tax instalments at April 15, June 15, September 15 and January 15 of the following year, with a weekend or holiday pushing the date to the next business day. The intervals are deliberately uneven — three months, two, three, then four — which is what makes the pattern worth memorising. The 15th of March and December belongs to corporate instalments, the first-of-the-month set matches no federal schedule, and starting in January shifts every date into the wrong quarter.
IRC §6654(c)(2)Under IRC §6041/§6041A (mirrored by Rev. & Tax Code §18631), service payments to a non-corporate payee are reported on Form 1099-NEC once they reach the annual threshold, which for tax year 2026 is $2,000, raised from the long-standing $600, so $3,400 is reportable (c). (a) is wrong because CSLB licensure has nothing to do with federal or state information reporting; only payments to corporations, other than legal and medical, are generally exempt. (b) picks the right reasoning but the wrong form: since tax year 2020 the 1099-MISC no longer carries nonemployee compensation, which moved out of its Box 7 to the 1099-NEC. (d) is for employees; a subcontractor is not on payroll and receives no W-2.
Internal Revenue Code §6041 (CA Rev. & Tax §18631)B&P §7071.17(a) makes the board require, before it will issue, renew, reinstate or reactivate, a bond sufficient to guarantee payment of an amount equal to the unsatisfied final judgment or judgments; the applicant has 90 days to file it, it stays on file at least a year, and a notarised accord with the judgment holder may be given instead. It is in addition to the contractor's bond. A second licence bond leaves the judgment itself unsecured, and §7071.11(b) bars renewal while a judgment above the bond amount is unpaid. No $5,000 deposit option exists, and a surety release letter is a status letter rather than security.
Bus. & Prof. Code §7071.17(a)Bidder's security, usually a bid bond, protects the awarding body against an apparent low bidder that refuses to execute the contract or to post the performance and payment bonds Public Contract Code §10221 requires; the surety then pays the lesser of the bond amount or the difference between that bid and the next acceptable bid. Payment of subcontractors and suppliers is the payment bond's promise under Civil Code §9550. Completion on schedule is the performance bond's promise. Workmanship defects are covered by the contract's warranty terms, not by a bond posted with the bid.
Public Contract Code §20170; §10221B&P §7159.5(a)(3) caps the down payment on a home improvement contract at $1,000 or 10 percent of the contract amount, whichever is less, so on a $60,000 job the ceiling is $1,000 and not $6,000; §7159.5(a)(5) then forbids requesting or accepting any later payment that exceeds the value of work performed or material delivered. Dropping the dollar cap, as the 10 percent and 20 percent options do, is exactly the error the statute prevents on larger contracts. The $5,000 and 25 percent figures appear in no California contract type.
B&P §7159.5(a)(3), (a)(5)Bus. & Prof. Code §7159.5 establishes special, stricter rules for residential swimming pool contracts: the down payment cannot exceed $200, and the balance must be paid in milestone-based progress payments matching the actual stages of pool construction (e.g., excavation, steel, plumbing, gunite, decking, plaster). The $1,000/10% rule in option A applies to general home improvement under §7159 — pools have their own tighter rule. The 20% and $5,000 options would violate consumer-protection requirements and are common CSLB discipline triggers.
Bus. & Prof. Code §7159.5The licence bond is a fixed pool: recovery cannot exceed its $25,000 penal sum, and B&P §7071.11(a) provides that if the bond is insufficient to pay all claims in full, the sum is distributed to all claimants in proportion to the amount of their respective claims. There is no priority ladder and no consumer-fraud sub-limit; the only category ceiling is $4,000 on the surety's aggregate liability for wage and fringe benefit claims. A bond is not secondary security that tops up a judgment. And California has no CSLB recovery fund for general consumer claims, though §7071.11(b) blocks renewal while the unpaid balance stands and the consumer may still pursue the contractor for it.
Bus. & Prof. Code §7071.11(a); §7071.11(b)Want these explained in order? CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
B&P §7071.11(a) is one sentence: if the bond cannot pay all claims in full, "the sum of the bond shall be distributed to all claimants in proportion to the amount of their respective claims." There is no ladder — a homeowner, an unpaid framer and a supplier all take the same percentage of what they are owed (a). (d) is the trap, and it is seductive because the section DOES single out wages once: the surety's aggregate liability for wage and fringe-benefit claims on this bond is capped at $4,000. That is a ceiling on one category, not a head start for it. (b) inverts the purpose of a bond, which exists for claimants and not for the surety or the board. (c) is the rule for recording real-property interests, not for bond proceeds.
Bus. & Prof. Code §7071.11(a)B&P §7071.12 lets a licensee deposit cash, a cashier's check or specified securities in the full amount of the bond it replaces, and the deposit goes to the State Treasurer, where it answers claims on the same terms as a surety bond and is distributed pro rata under §7071.11(a) if it is not enough. There is no leverage ratio, so a $5,000 deposit secures nothing. There is no partial substitution either: cash and surety cannot be mixed to reach the figure. And a private bank escrow, however well insured, is not a deposit with the Treasurer.
Bus. & Prof. Code §7071.12; §7071.11(a)An RMO is an officer of the licensed entity; an RME is a bona fide employee permanently employed by it, and 16 CCR §823 requires a qualifier who is not a bona fide owner to exercise direct supervision and control for at least 32 hours a week or 80 percent of the hours the business operates, whichever is less. Ownership of 10 percent or more is what relieves a qualifier of that hours test, so it describes the exemption rather than the RME. Family ties appear nowhere in §7068.1. And the licence class follows the work the entity is qualified for, not a personal credential the RME must hold.
B&P §7068.1; 16 CCR §823Misclassification stacks two kinds of liability. The tax side is federal income tax withholding and both FICA shares under IRC §3402 and §3111, FUTA under §3301, and California PIT, SDI and UI through the EDD, with the reduced rates of IRC §3509 available only if the failure was not wilful. The labour side is a Labor Code §226.8 penalty of $5,000 to $15,000 per wilful violation, or $10,000 to $25,000 where there is a pattern, plus wage-statement penalties under §226(e) and uninsured-employer exposure for workers' compensation. A signed acknowledgment changes nothing, because Labor Code §2775(a) disregards the label the parties use. And the information-return penalty is a rounding error beside the rest.
Labor Code §226.8; §2775(a); IRC §3509Civil Code §8811, added by SB 61 and operative for contracts entered into on or after January 1, 2026, caps retention on a private work of improvement at 5 percent — of each payment and of the contract price — at every tier: owner to direct contractor, direct contractor to subcontractor, and below (b). The two exceptions behind the word 'narrow' are a residential project that is not mixed use and does not exceed four stories, and a subcontractor that fails to furnish a performance and payment bond from an admitted surety after written notice given at or before bid time. The prevailing party in an action to enforce the section recovers attorney's fees. (a) states the law as it stood before 2026, when private retention really was a pure matter of contract. (c) is the 10 percent custom the statute was passed to end; it now survives only inside those two exceptions and on contracts signed before 2026. (d) has the right figure but the wrong scope — Public Contract Code §7201 has capped most state and local public works at 5 percent for years, and §8811 extends the same ceiling to private work.
Civil Code §8811; Public Contract Code §7201B&P §7071.6, as amended by SB 607, raised the contractor licence bond from $15,000 to $25,000 effective 1 January 2023, and the Bond of Qualifying Individual under §7071.9 rose to $25,000 with it; the LLC employee and worker bond under §7071.6.5 is $100,000. $15,000 and $12,500 are pre-2023 figures, and $12,500 was the amount before 2016. No class of licence carries a $50,000 bond.
Bus. & Prof. Code §7071.6 (SB 607, 2021)B&P §7071.9 requires a separate $25,000 bond of qualifying individual whenever the RMO or RME is not a bona fide owner of at least 10 percent of the licensed entity, because a qualifier with no real stake has less at risk if supervision lapses, and the bond gives the public a second source of recovery. Headcount is irrelevant to §7071.9. Holding more than one classification changes the scope of work, not the bonding. And self-insuring workers' compensation is a separate Labor Code §3700 process with its own security requirements.
Bus. & Prof. Code §7071.9Markup is calculated on cost. $8,000 x 25% = $2,000 markup. Price = $8,000 + $2,000 = $10,000. (Note: a 25% markup is NOT the same as a 25% margin; a 25% margin would produce a price of $8,000 / 0.75 = $10,666.)
Gross profit = $15,000 - $12,000 = $3,000. Margin is profit divided by SELLING price: $3,000 / $15,000 = 0.20 = 20%. (The markup, by contrast, would be $3,000 / $12,000 = 25%.)
For a target margin, divide cost by (1 - margin). Selling price = $6,000 / (1 - 0.40) = $6,000 / 0.60 = $10,000. Check: profit = $10,000 - $6,000 = $4,000, and $4,000 / $10,000 = 40% margin. Marking up 40% on cost ($8,400) would give only a 28.6% margin, a common and costly error.
Take cost = $100. A 50% markup adds $50, giving a price of $150. Margin = profit / price = $50 / $150 = 33.3%. Markup and margin are different: markup is on cost, margin is on price.
Markup = profit / cost. Profit = $20,000 - $16,000 = $4,000. Markup = $4,000 / $16,000 = 0.25 = 25%. (The margin on price would be $4,000 / $20,000 = 20%.)
The markup that yields a given margin = margin / (1 - margin). Here 0.30 / 0.70 = 0.4286 = 42.9%. Check with cost $100: 42.9% markup gives price $142.90; margin = $42.90 / $142.90 = 30%.
$2,000 x 35% = $700 markup. Price = $2,000 + $700 = $2,700. Markup is added to cost.
Margin states profit as a percentage of the selling PRICE; markup states the same dollar profit as a percentage of COST. Because price is the larger base, margin is always the smaller percentage, which is why the first option has it backwards. The third option swaps the bases outright. The fourth would hold only if cost equalled price, which would mean no profit at all.
Margin 20% means profit is 20% of the $50,000 price = $10,000. Costs = price - profit = $50,000 - $10,000 = $40,000.
100% markup doubles cost: price = $3,000 + $3,000 = $6,000. Margin = profit / price = $3,000 / $6,000 = 50%. A 100% markup always equals a 50% margin.
Overhead recovery rate = annual overhead / annual direct costs = $120,000 / $600,000 = 0.20 = 20%. He adds 20% of each job's direct cost to cover overhead, then adds profit on top.
Overhead consists of indirect costs that keep the business running but are not tied to one specific job, such as office rent, administrative salaries, insurance, and utilities. Materials, on-site labor, and subcontractors are direct costs charged to a particular job.
Direct cost $10,000 + 15% overhead ($1,500) = $11,500 subtotal. Then 10% profit on $11,500 = $1,150. Final price = $11,500 + $1,150 = $12,650. Order matters: overhead first, then profit on the total.
Overhead is the indirect, ongoing cost of running the business — rent, office wages, insurance, trucks, licences — which cannot be billed to any single job and must be recovered across all of them through markup. Costs that scale with the job are direct costs, and materials and labour for a job are the clearest example of direct cost. What is left after every cost is paid is net profit, which comes after overhead rather than being it.
Net profit = revenue - direct costs - overhead = $800,000 - $560,000 - $160,000 = $80,000. Net profit margin = $80,000 / $800,000 = 10%.
When the overhead rate built into the markup is too low, every bid is priced below the true cost of doing business: the job can show a profit on its own sheet while the company loses money once real overhead is paid. Bidding high is the result of the opposite error, over-recovering overhead. Lower taxes follow a lower profit but are a symptom, not the harm. And subcontractors price their own overhead into their own numbers; nothing shifts the general contractor's overhead onto them.
Break-even revenue = fixed costs / contribution margin ratio = $90,000 / 0.30 = $300,000. At $300,000 revenue, the 30% contribution margin ($90,000) exactly covers fixed costs, leaving zero profit.
Break-even units = fixed costs / contribution margin per job = $60,000 / $2,000 = 30 jobs. Below 30 jobs he loses money; above 30 he earns profit.
Break-even is the sales volume at which total revenue equals total costs, fixed and variable together, so the result is neither profit nor loss. Covering overhead alone is not break-even, because direct job costs still have to be paid. Variable costs equalling fixed costs is an arbitrary coincidence with no meaning for profit. Maximum profit is a different point entirely, and it lies well above break-even.
Required revenue = (fixed costs + target profit) / contribution margin ratio = ($100,000 + $50,000) / 0.25 = $150,000 / 0.25 = $600,000.
Break-even revenue = fixed costs / contribution margin ratio. Raising the numerator (fixed costs) while holding the ratio constant increases the break-even sales volume: he must sell more just to cover the higher fixed costs.
Materials are 3,200 x $0.85 = $2,720 and labour is 40 x $45 = $1,800, so the direct cost is $4,520. $3,920 comes from pricing the labour at $30 an hour instead of $45. $4,840 comes from reading the lumber at $0.95 a board foot. $2,720 is the materials alone, with the labour line left out of the estimate.
Overrun = (actual - estimate) / estimate = (150 - 120) / 120 = 30 / 120 = 0.25 = 25%. Job costing compares estimated to actual to reveal a 25% labor overrun.
Job costing records the labour, material, subcontract and equipment cost actually incurred on each project and sets it beside the estimate, so the contractor learns which jobs made money and bids the next one better. Spreading overhead is what the overhead rate does, and it is an input to the bid rather than the purpose of job costing. Sales tax is computed from purchase invoices. And an hourly price for the next job is guesswork unless the job history behind it has been costed.
Volume in cubic feet = 30 x 40 x (4/12) = 30 x 40 x 0.333 = 400 cubic feet. Convert to cubic yards: 400 / 27 = 14.8 cubic yards.
Burden adds 35% to the base wage: $28 x 1.35 = $37.80 per hour. Estimators must use the fully burdened rate, not the base wage, or labor will be underestimated.
One coat: 2,400 / 350 = 6.86, round up to 7 gallons. Two coats need 2 x 6.86 = 13.7, round up to 14 gallons. Always round up when buying whole cans.
Markup = $18,000 x 12% = $2,160. Amount billed = $18,000 + $2,160 = $20,160. The general marks up subcontracts to cover coordination, supervision, and risk.
A contingency is money set aside inside the estimate to absorb unforeseen site conditions and the normal imprecision of estimating, so a small surprise does not have to become a claim. It is not profit: spending it leaves the margin intact, while treating it as profit means pricing the risk twice. Retention is the owner's money withheld from payments - five percent on public works under Public Contract Code section 7201, and capped at five percent on private contracts entered into on or after 1 January 2026 by Civil Code section 8811 - so it is money not yet received rather than a cost to fund. And owner-requested changes are paid through change orders at agreed prices, which is why they sit outside the contingency.
Public Contract Code §7201; Civil Code §8811Working capital is current assets minus current liabilities, the short-term money actually available to run the business. Total assets minus total liabilities is owner's equity, which measures net worth rather than liquidity. Revenue minus operating expenses is operating profit, a period result rather than a balance. And cash minus payables ignores receivables, inventory and the rest of the current accounts, so it understates what is on hand to work with.
Working capital = current assets - current liabilities = $150,000 - $90,000 = $60,000. This is the cash cushion available for short-term obligations.
The structural cause is timing: wages and material invoices fall due weeks before the owner pays a progress billing, and retention delays part of the receipt further still, so cash drains even on a profitable job. Taking an early-payment discount does consume cash, but it buys a return and is a choice rather than the cause. Monthly billing lengthens the gap and makes the problem worse, without being its origin. Withholding retention from subs conserves the contractor's cash rather than draining it.
Accrual accounting books revenue when it is earned, but wages, suppliers and taxes must be paid in cash immediately, and money sitting in receivables, retention and work in progress is not available to spend. Double-recording revenue would be an error, not a reason. Depreciation is the opposite case: it reduces book profit without any cash leaving the bank. And retention is recorded as a receivable, an asset still owed, which is precisely why profit can look healthy while the bank balance does not.