California Civil Engineer: Seismic Principles — All Questions

300 questions

Seismic Analysis Procedures

Which elements must be designed with the overstrength factor when a shear wall is discontinued and supported on columns below?

  • a.The columns, beams or slabs that support the discontinuous wall✓
  • b.The nonstructural partitions located in the story below the wall
  • c.The roof diaphragm sheathing located directly above the wall
  • d.The foundations of the unrelated walls in the perpendicular direction

ASCE 7-16 Section 12.3.3.3 requires structural elements supporting discontinuous walls or frames to be designed for seismic load effects including overstrength. The supporting elements must stay elastic while the wall above reaches its real strength; their failure would remove gravity support.

Seismic Analysis Procedures

With seismic load effects including overstrength, what value is used for the redundancy factor?

  • a.Rho is taken as 1.5
  • b.Rho is taken as 1.0✓
  • c.Rho is taken as 1.3
  • d.Rho equals the overstrength factor

ASCE 7-16 Section 12.3.4.1 lists members designed for load combinations with overstrength among the cases where rho = 1.0. Overstrength already estimates the maximum force the system can deliver, so a redundancy penalty on top is not required.

Seismic Analysis Procedures

For allowable stress design, which basic combination governs overturning (uplift) of a shear wall?

  • a.D + 0.75L + 0.525E
  • b.1.0D + 0.7E
  • c.1.4D + 1.0E
  • d.0.6D + 0.7E✓

ASCE 7-16 Section 2.4.5 pairs 0.6D with 0.7E (expanding to (0.6 - 0.14 SDS)D + 0.7 rho QE) to minimize the stabilizing dead load. Combinations with full D check maximum compression, and 1.4D is a strength-design gravity combination.

Seismic Analysis Procedures

Using the rigidity relationship, how does a fixed-fixed wall pier compare with a cantilever pier of the same dimensions?

  • a.Both have identical rigidity, because rigidity depends on the area only
  • b.The fixed-fixed pier is stiffer, because its flexural deflection term is smaller✓
  • c.The cantilever pier is stiffer, because it is free to rotate at the top
  • d.The fixed-fixed pier is more flexible, because it must bend in double curvature

For a rectangular pier the deflection is proportional to (h/d)^3 + 3(h/d) when fixed at both ends and 4(h/d)^3 + 3(h/d) when cantilevered. The shear term is identical, but the flexural term is one-quarter as large for the fixed-fixed case, so its rigidity (1/deflection) is higher.

Seismic Analysis Procedures

How is the lateral rigidity of a wall defined?

  • a.The ratio of the wall height to the wall plan length
  • b.The deflection that is produced by the wall's own weight
  • c.The area of the wall divided by the story height
  • d.The force required to produce a unit lateral deflection✓

Rigidity (stiffness) k = F/delta, the reciprocal of the deflection under a unit load. Aspect ratio h/d strongly influences rigidity but is not the rigidity itself; relative rigidities are what matter for distributing rigid-diaphragm forces.

Seismic Analysis Procedures

Several wall piers between openings act side by side along one wall line. How is the combined rigidity of the piers obtained?

  • a.By using the rigidity of the single most flexible pier
  • b.By adding the individual pier rigidities, since they are in parallel✓
  • c.By adding the individual pier deflections, since they are in series
  • d.By averaging the heights of the piers and using one pier

Piers connected by a common top spandrel or diaphragm deflect together, so they act in parallel and rigidities add. Deflections add for elements in series, such as a strip of piers stacked on a solid portion of wall below the openings.

Seismic Analysis Procedures

A one-story building has shear walls on only three sides (open front) and a wood diaphragm. How is lateral load toward the open side resisted?

  • a.By uplift of the roof sheathing nails along the open-front edge header
  • b.By diaphragm rotation, with the two side walls resisting the torsion as a couple✓
  • c.By the rear wall alone in direct shear, with no force in the side walls
  • d.By bending of the open-front gravity columns acting as the primary lateral system

With no wall line at the open front, load parallel to the rear wall is carried by the rear wall in direct shear, and the resulting eccentricity is resisted by a couple in the two side walls. SDPWS-2021 Section 4.2 limits the proportions and conditions for such open-front, cantilevered diaphragms.

Seismic Analysis Procedures

In the modal response spectrum procedure, to what value must the combined modal base shear be scaled if it is lower?

  • a.No scaling is required in ASCE 7-16
  • b.50% of the equivalent lateral force base shear
  • c.100% of the equivalent lateral force base shear✓
  • d.85% of the equivalent lateral force base shear

ASCE 7-16 Section 12.9.1.4.1 requires force results to be scaled up when the modal base shear is less than 100% of the ELF base shear; the 85% scaling was the rule in ASCE 7-10 and earlier. This keeps a computer model with a long period from producing unconservatively low forces.

Seismic Analysis Procedures

When may the equivalent lateral force distribution be used to design diaphragm collectors in SDC D without overstrength?

  • a.In structures braced by special reinforced concrete shear walls
  • b.In any structure with a rigid concrete diaphragm
  • c.In structures braced entirely by light-frame shear walls✓
  • d.In any structure assigned to Risk Category IV

ASCE 7-16 Section 12.10.2.1 requires overstrength for collectors in SDC C through F, with an exception for structures or portions braced entirely by light-frame shear walls, where collectors need only be designed for the diaphragm forces of Section 12.10.1.1.

Seismic Analysis Procedures

What is a subdiaphragm?

  • a.A portion of a larger diaphragm designed to transfer wall anchorage forces to the continuous crossties✓
  • b.A plywood overlay nailed on top of the existing roof sheathing in order to raise its shear capacity
  • c.A horizontal steel truss that replaces the sheathing in a long-span diaphragm
  • d.A secondary roof built below the main roof to carry suspended mechanical units

A subdiaphragm is a small diaphragm within the main one, with its own chords and shear capacity, that picks up out-of-plane wall anchorage forces and delivers them to continuous crossties. ASCE 7-16 Section 12.11.2.2.1 limits its length-to-width ratio to 2.5 to 1.

Seismic Analysis Procedures

What is the maximum length-to-width ratio of a structural subdiaphragm used for wall anchorage?

  • a.4 to 1
  • b.6 to 1
  • c.2.5 to 1✓
  • d.1 to 1

ASCE 7-16 Section 12.11.2.2.1 limits the subdiaphragm length-to-width ratio to 2.5 to 1. The limit keeps the subdiaphragm stiff enough to deliver anchorage forces to the main diaphragm crossties without excessive deformation.

Seismic Analysis Procedures

In a wood shear wall, what resists the overturning moment caused by the lateral force at the top of the wall?

  • a.The edge nailing of the sheathing to the top plates only
  • b.The roof diaphragm chord over the top of the wall line
  • c.Hold-downs and end posts, forming a tension-compression couple✓
  • d.The anchor bolts acting in shear along the length of the sill

The lateral force times wall height produces overturning resisted by tension in a hold-down (tie-down) at one end and compression in the end post at the other, less any dead load. Sill anchor bolts transfer the horizontal shear to the foundation, a separate job.

Seismic Analysis Procedures

For a wood structural panel shear wall, the tie-down tension force before dead load is approximately what?

  • a.Total shear divided by the wall height
  • b.Total shear times the wall length
  • c.Unit shear times the wall length
  • d.Unit shear times the wall height✓

Overturning moment = V x h, resisted by a couple with lever arm roughly the wall length b: T = Vh/b = (V/b)h = v x h. So the uplift equals unit shear times height. Multiplying by length instead gives the total wall shear, not the uplift.

Seismic Analysis Procedures

Which load combination gives the maximum compression on a column for strength design with seismic load?

  • a.(0.9 - 0.2 SDS)D + rho QE
  • b.(0.6 - 0.14 SDS)D + 0.7 rho QE + 0.75L
  • c.(1.2 + 0.2 SDS)D + rho QE + L + 0.2S✓
  • d.1.4D with no earthquake load

ASCE 7-16 Section 2.3.6 with Section 12.4.2: the additive combination 1.2D + Ev + Eh + L + 0.2S expands to (1.2 + 0.2 SDS)D + rho QE + L + 0.2S and maximizes compression. The 0.9D form minimizes dead load for uplift, and the 0.6D form is its ASD counterpart.

Seismic Detailing and Construction Quality Control

A wall anchorage system in a flexible-diaphragm building is designed for a strength-level force of 1,150 lb/ft. For what force must the steel elements of the anchorage system (other than anchor bolts and reinforcing steel) be designed?

  • a.805 lb/ft
  • b.1,150 lb/ft
  • c.1,438 lb/ft
  • d.1,610 lb/ft✓

ASCE 7-16 Section 12.11.2.2.2 increases the strength design forces for steel elements of the structural wall anchorage system by 1.4: 1.4 x 1,150 = 1,610 lb/ft. The factor guards against low-ductility fracture of straps and hardware, the failure seen in Northridge tilt-up roofs. Anchor bolts and reinforcing steel are excluded from the increase, and 0.7 is an allowable-stress conversion, not a detailing factor.

Seismic Detailing and Construction Quality Control

A wall anchorage system in a flexible-diaphragm building is designed for a strength-level force of 1,600 lb/ft. For what force must the steel elements of the anchorage system (other than anchor bolts and reinforcing steel) be designed?

  • a.1,600 lb/ft
  • b.2,000 lb/ft
  • c.2,240 lb/ft✓
  • d.3,200 lb/ft

ASCE 7-16 Section 12.11.2.2.2 increases the strength design forces for steel elements of the structural wall anchorage system by 1.4: 1.4 x 1,600 = 2,240 lb/ft. The factor guards against low-ductility fracture of straps and hardware, the failure seen in Northridge tilt-up roofs. Anchor bolts and reinforcing steel are excluded from the increase, and 0.7 is an allowable-stress conversion, not a detailing factor.

Seismic Detailing and Construction Quality Control

A wall anchorage system in a flexible-diaphragm building is designed for a strength-level force of 860 lb/ft. For what force must the steel elements of the anchorage system (other than anchor bolts and reinforcing steel) be designed?

  • a.602 lb/ft
  • b.860 lb/ft
  • c.1,075 lb/ft
  • d.1,204 lb/ft✓

ASCE 7-16 Section 12.11.2.2.2 increases the strength design forces for steel elements of the structural wall anchorage system by 1.4: 1.4 x 860 = 1,204 lb/ft. The factor guards against low-ductility fracture of straps and hardware, the failure seen in Northridge tilt-up roofs. Anchor bolts and reinforcing steel are excluded from the increase, and 0.7 is an allowable-stress conversion, not a detailing factor.

Seismic Detailing and Construction Quality Control

What is the intent of the strong-column/weak-beam requirement in special moment frames?

  • a.To keep every member of the frame elastic in the design earthquake
  • b.To make beams yield before columns so a story mechanism does not form✓
  • c.To make the beam-column joints yield before any member reaches yield
  • d.To make columns yield before beams so the floors remain undamaged

If columns hinge at the top and bottom of one story, all the drift concentrates there and collapse can follow. Requiring column flexural strength to exceed beam strength at each joint spreads yielding into beams over many stories. Special frames are expected to yield, not stay elastic.

Seismic Detailing and Construction Quality Control

In special concrete moment frames, why are closely spaced hoops with 135-degree hooks required in column end regions?

  • a.To confine the core and restrain bar buckling in plastic hinge zones✓
  • b.To allow lap splices to be placed directly within the hinge zones
  • c.To increase the column's elastic stiffness under service gravity loads
  • d.To reduce the amount of longitudinal steel that the column needs

Confinement keeps the core concrete and longitudinal bars working after the cover spalls, and 135-degree hooks stay anchored in the core where 90-degree hooks open up. Lap splices are in fact kept out of hinge zones, toward the column midheight.

Seismic Detailing and Construction Quality Control

Where should lap splices of longitudinal bars be located in a special moment frame column?

  • a.At the face of the footing
  • b.Within the center half of the column height✓
  • c.Within the beam-column joint
  • d.Immediately above the top of the floor slab

ACI 318 (adopted by the CBC) restricts lap splices in special moment frame columns to the center half of the member length, designed as tension splices and enclosed in transverse reinforcement, because the ends are the likely hinge regions where cover spalls and splices fail.

Seismic Detailing and Construction Quality Control

What is the purpose of boundary elements in a special reinforced concrete shear wall?

  • a.To eliminate the need for horizontal shear reinforcement in the wall web
  • b.To provide a ledge for supporting the floor diaphragm framing
  • c.To isolate the wall from the foundation with a sliding joint
  • d.To confine the highly compressed wall edges so they sustain large strains✓

Under overturning, the wall ends see high compressive strain; closely tied boundary elements confine the concrete and prevent bar buckling so the wall can yield in flexure without crushing. They do not replace web shear reinforcement.

Seismic Detailing and Construction Quality Control

In a special concentrically braced frame, which element is intended to be the primary source of inelastic energy dissipation?

  • a.The gusset plate welds, through controlled fracture
  • b.The braces, through tension yielding and compression buckling✓
  • c.The anchor rods, through inelastic elongation at the base plates
  • d.The columns, through plastic hinging at the midheight

AISC 341 (referenced by the CBC) details SCBF braces to buckle and yield cyclically while connections, beams and columns are designed for the expected brace strength. Weld fracture or column hinging is exactly what capacity design is meant to prevent.

Seismic Detailing and Construction Quality Control

In an eccentrically braced frame, which element is designed to yield?

  • a.The diagonal brace member
  • b.The column base plate
  • c.The floor slab outside the frame
  • d.The link segment of the beam✓

EBFs concentrate inelastic action in the link, the short beam segment between brace connections or between a brace and a column, which yields in shear or flexure. Braces, columns and beam segments outside the link are designed to stay essentially elastic for the forces from a fully yielded, strain-hardened link.

Seismic Detailing and Construction Quality Control

What distinguishes a buckling-restrained brace from a conventional brace?

  • a.It is made of concrete only and so has no yielding steel element
  • b.Its steel core is designed to buckle elastically before it can yield
  • c.It resists load in tension only and goes slack under compression
  • d.Its steel core yields in both tension and compression without buckling✓

A buckling-restrained brace has a steel core inside a restraining casing (typically a mortar-filled tube) with an unbonding layer, so the core yields in compression as well as tension, giving stable, symmetric hysteresis. Conventional braces lose strength when they buckle.

Seismic Detailing and Construction Quality Control

What is a 'protected zone' in a steel special moment frame?

  • a.A fire-rated enclosure built around the beam-to-column connection
  • b.A portion of the column encased in concrete for corrosion and impact protection
  • c.A region expected to yield where attachments and discontinuities are restricted✓
  • d.A section of the frame that is exempt from special inspection

AISC 341 designates regions of expected inelastic strain, such as beam plastic hinge zones, as protected zones: no shear studs, welded or shot-in attachments, or other notch-forming discontinuities are permitted there because they can initiate fracture.

Seismic Detailing and Construction Quality Control

After Northridge, how do prequalified steel moment connections such as the reduced beam section improve performance?

  • a.They eliminate all welding by using only snug-tight bolted connections
  • b.They concentrate yielding in the weld metal at the face of the column
  • c.They move the plastic hinge into the beam, away from the column-face welds✓
  • d.They stiffen the beam so that the frame remains elastic at any drift

Trimming the beam flanges a short distance from the column forces yielding to occur in the reduced section, protecting the welded joint. AISC 358 prequalifies such connections on the basis of cyclic testing. Yielding in welds was the pre-Northridge failure mode.

Seismic Detailing and Construction Quality Control

Which masonry shear wall type is required for a masonry seismic force-resisting system in Seismic Design Category D?

  • a.Ordinary reinforced masonry shear walls
  • b.Detailed plain masonry shear walls
  • c.Special reinforced masonry shear walls✓
  • d.Ordinary plain masonry shear walls

ASCE 7-16 Table 12.2-1 and TMS 402-16 Section 7.3.2 permit only special reinforced masonry shear walls in SDC D, E and F. Plain (unreinforced) and ordinary reinforced types are limited to lower design categories.

Seismic Detailing and Construction Quality Control

For special reinforced masonry shear walls, what is the minimum sum of the vertical and horizontal reinforcement areas?

  • a.0.002 times the gross cross-sectional area✓
  • b.0.01 times the gross cross-sectional area
  • c.0.04 times the gross cross-sectional area
  • d.0.0007 times the gross cross-sectional area

TMS 402-16 Section 7.3.2.6 requires the sum of vertical and horizontal reinforcement to be at least 0.002 times the gross area, with at least 0.0007 in each direction. One percent and four percent are column-type limits, not wall minimums.

Seismic Detailing and Construction Quality Control

What is the maximum spacing of reinforcement in a special reinforced masonry shear wall, apart from the limits tied to wall length and height?

  • a.120 in.
  • b.96 in.
  • c.48 in.✓
  • d.16 in.

TMS 402-16 Section 7.3.2.6 limits vertical and horizontal reinforcement spacing to the smallest of one-third the wall length, one-third the wall height, and 48 in. (tighter for stack bond). The 120-in. spacing belongs to ordinary reinforced walls.

Seismic Detailing and Construction Quality Control

For wall anchorage in Seismic Design Categories C through F, which connection is prohibited?

  • a.Hold-down hardware bolted to purlins or to subpurlins
  • b.Cast-in anchors embedded in a reinforced bond beam
  • c.Steel straps hooked around the wall's horizontal reinforcing bars
  • d.Wood ledgers loaded in cross-grain bending or cross-grain tension✓

ASCE 7-16 Section 12.11.2.2.3 prohibits anchorage that puts wood ledgers or framing in cross-grain bending or tension, the detail that failed in 1971 when ledgers split along the bolt line. Straps, hold-downs and embedded anchors that deliver force directly into framing are the accepted details.

Seismic Detailing and Construction Quality Control

In a wood diaphragm providing wall anchorage for a concrete wall in SDC D, which of these may NOT serve as the required continuous tie?

  • a.The diaphragm sheathing itself✓
  • b.Purlins with tension straps across girders
  • c.Steel straps nailed along blocking lines
  • d.Continuous girders with spliced ends

ASCE 7-16 Section 12.11.2.2.3 states that in wood diaphragms the continuous ties are in addition to the sheathing; sheathing is not considered effective as a tie or strut, and toenails or nails in withdrawal cannot provide anchorage. Framing members with positive splices form the ties.

Seismic Detailing and Construction Quality Control

Embedded steel straps are used to anchor a concrete wall to a wood roof. What does ASCE 7-16 require of the strap embedment?

  • a.Straps attached to or hooked around reinforcing steel so force reaches it✓
  • b.Straps bonded to the face of the wall with a structural epoxy adhesive
  • c.Straps cast into the slab on grade rather than into the wall panel
  • d.Straps embedded at least 2 in. into plain, unreinforced concrete

ASCE 7-16 Section 12.11.2.2.5: diaphragm-to-wall anchorages using embedded straps shall be attached to, or hooked around, the reinforcing steel or otherwise terminated so as to effectively transfer forces to the reinforcing. A shallow strap in plain concrete can pull out a cone of concrete.

Seismic Detailing and Construction Quality Control

What does the deformation compatibility requirement for Seismic Design Categories D through F demand of gravity-only framing?

  • a.It must be designed with the same R factor as the lateral force system
  • b.It must be separated from the diaphragm so that it does not move laterally
  • c.It must sustain its gravity loads while deforming through the design story drift✓
  • d.It must be designed to resist at least 25% of the design seismic base shear by itself

ASCE 7-16 Section 12.12.5 requires every structural component not included in the seismic force-resisting system to be adequate for gravity load effects and the forces resulting from the design story drift. Gravity columns and slab connections ride along with the building and must not fail as it sways.

Seismic Detailing and Construction Quality Control

Each smaller portion of a structure must be tied to the remainder with elements able to transmit what minimum seismic force?

  • a.The lesser of 0.044 SDS times the smaller portion's weight or 1% of its weight
  • b.The greater of 0.133 SDS times the smaller portion's weight or 5% of its weight✓
  • c.The greater of 0.4 SDS times the total building weight or 10% of that weight
  • d.The greater of 1.6 SDS times the smaller portion's weight or 50% of its weight

ASCE 7-16 Section 12.1.3 requires interconnection of all parts of the structure with a design strength of at least 0.133 SDS times the weight of the smaller portion, or 5% of that weight, whichever is greater, so that parts cannot separate and lose support.

Seismic Detailing and Construction Quality Control

What minimum horizontal force must the connection of a beam, girder or truss to its support resist, acting parallel to the member?

  • a.25% of the live load reaction only
  • b.1% of the dead load reaction only
  • c.50% of the dead plus live load reaction
  • d.5% of the dead plus live load reaction✓

ASCE 7-16 Section 12.1.4 requires a positive connection for each beam, girder or truss with a design strength of at least 5% of the dead plus live load reaction, resisting force parallel to the member, so supports are not lost through sliding.

Seismic Detailing and Construction Quality Control

Under CBC Chapter 17, who prepares the statement of special inspections?

  • a.The building official's plan check engineer
  • b.The special inspector assigned to the project
  • c.The registered design professional in responsible charge✓
  • d.The general contractor's project manager or superintendent

CBC Section 1704.3 requires the statement of special inspections to be prepared by the registered design professional in responsible charge and submitted with the permit application. The contractor separately acknowledges responsibilities, and the special inspector carries out, rather than defines, the program.

Seismic Detailing and Construction Quality Control

Under CBC Section 1704.2, who is responsible for employing the special inspection agency?

  • a.The owner or the owner's authorized agent, other than the contractor✓
  • b.The subcontractor whose work is being inspected
  • c.The material supplier furnishing the products
  • d.The general contractor who is performing the work to be inspected

CBC Section 1704.2 makes the owner or the owner's authorized agent, other than the contractor, responsible for employing approved agencies, to keep the inspector independent of the party whose work is being inspected.

Seismic Detailing and Construction Quality Control

How does structural observation differ from special inspection under the CBC?

  • a.It is continuous testing of structural materials performed by an approved testing laboratory at the site
  • b.It is the contractor's own quality control check made before each concrete placement
  • c.It is the building official's final inspection made before a certificate of occupancy
  • d.It is visual observation of the structural system by a design professional for general conformance✓

CBC Sections 202 and 1704.6 define structural observation as visual observation of the structural system by a registered design professional for general conformance to the approved construction documents. It does not replace the detailed special inspections of Section 1705 or the building official's inspections.

Seismic Detailing and Construction Quality Control

At the conclusion of the work, what must the structural observer submit?

  • a.A written statement to the building official that site visits were made, identifying unresolved deficiencies✓
  • b.A stamped set of as-built drawings showing every field change that the contractor made during the work
  • c.A warranty that the completed structure will not be damaged in an earthquake
  • d.A certificate of occupancy for the building, signed on behalf of the owner

CBC Section 1704.6 requires the structural observer to submit to the building official a written statement that the site visits have been made and identifying any reported deficiencies that, to the observer's knowledge, have not been resolved.

Seismic Detailing and Construction Quality Control

What is the difference between continuous and periodic special inspection?

  • a.Continuous means the inspector is present full time while the work is performed✓
  • b.Continuous means the inspector reviews the daily reports once the work is completed
  • c.Periodic means the inspector is present full time while the work is performed
  • d.Periodic means the building official, not a special inspector, performs it

CBC Section 202 defines continuous special inspection as full-time observation by the special inspector present where and when the work is being performed, and periodic special inspection as part-time or intermittent observation at intervals appropriate to the work.

Seismic Detailing and Construction Quality Control

For wood seismic force-resisting systems in SDC D, special inspection of nailing is not required when the sheathing fastener spacing is what?

  • a.Less than 4 in. on center
  • b.Less than 2 in. on center
  • c.Exactly 3 in. on center
  • d.More than 4 in. on center✓

CBC Section 1705.13.2 requires periodic special inspection of nailing, bolting and anchoring of wood shear walls, diaphragms, drag struts and hold-downs, with an exception where the fastener spacing of the sheathing is more than 4 in. on center. Tight nailing means high shear demand, which is where inspection matters.

Seismic Detailing and Construction Quality Control

Under the CBC, what special inspection applies to field gluing of elements of a wood seismic force-resisting system?

  • a.Periodic special inspection
  • b.No special inspection at all
  • c.Inspection by the contractor only
  • d.Continuous special inspection✓

CBC Section 1705.13.2 calls for continuous special inspection during field gluing operations of elements of the seismic force-resisting system, because a glue line cannot be evaluated after the fact. Nailing, bolting and anchoring receive periodic inspection.

Seismic Detailing and Construction Quality Control

Each contractor responsible for constructing a main seismic force-resisting system listed in the statement of special inspections must submit what?

  • a.A peer review report prepared by an independent licensed structural engineer
  • b.A geotechnical report confirming the site class used in the design
  • c.A written statement of responsibility to the building official and owner✓
  • d.A performance bond equal to the full value of the structural work

CBC Section 1704.4 requires each contractor responsible for construction of a main wind or seismic force-resisting system, designated seismic system or component listed in the statement of special inspections to submit a written statement of responsibility acknowledging awareness of the special requirements.

Seismic Detailing and Construction Quality Control

In wood shear walls with high unit shears, SDPWS requires 3-in. nominal or thicker framing at adjoining panel edges. What is the main reason?

  • a.To increase the gravity load capacity of the studs under the roof loads
  • b.To reduce the sound transmission through the wall between dwelling units
  • c.To prevent splitting where two rows of closely spaced nails share one member✓
  • d.To provide a wider bearing surface for the gypsum board interior finishes

SDPWS-2021 Section 4.3 requires wider framing (or equivalent) at adjoining panel edges with close nail spacing, with nails staggered, because two lines of closely spaced nails in a 2x member split it and the wall loses capacity.

Seismic Detailing and Construction Quality Control

Why does SDPWS call for steel plate washers on foundation anchor bolts of wood shear walls?

  • a.To insulate the anchor bolt from moisture in the concrete
  • b.To restrain the sill plate against cross-grain bending and splitting✓
  • c.To allow the sill plate to slide during an earthquake
  • d.To increase the shear capacity of the foundation concrete at the bolt

Sheathing uplift on one edge of the sill puts it in cross-grain bending; SDPWS-2021 Section 4.3.6.4.3 requires plate washers (commonly 0.229 in. x 3 in. x 3 in.) extending close to the sheathed edge to hold the sill down. Sills split along the bolt line in Northridge where small round washers were used.

Seismic Detailing and Construction Quality Control

What does blocking a wood structural panel diaphragm accomplish?

  • a.All panel edges are fastened to framing, raising shear capacity and stiffness✓
  • b.Panel edges are left free to slip, which lowers the force in the diaphragm chords
  • c.The roof framing is ventilated, so the sheathing remains dry in service
  • d.The sheathing nails are replaced, so that no edge nailing is needed

In a blocked diaphragm every panel edge lands on framing or blocking and is nailed, so shear transfers continuously between panels. SDPWS-2021 tabulates substantially higher capacities and lower deflections for blocked diaphragms than for unblocked ones.

Seismic Detailing and Construction Quality Control

Which weld in a steel special moment frame typically requires the highest level of quality control, including specified toughness?

  • a.Seal welds on architectural handrail base plate covers
  • b.Tack welds holding metal deck in position before the final fastening
  • c.Fillet welds attaching nonstructural ceiling hanger clips
  • d.Complete-joint-penetration groove welds of beam flanges to columns✓

AISC 341 designates CJP groove welds at beam flange-to-column joints (and similar) as demand critical, requiring filler metal with specified notch toughness, and CBC Chapter 17 through AISC 341 requires inspection and nondestructive testing of them.

Seismic Detailing and Construction Quality Control

For the seismic force-resisting system of structural steel buildings, which standard does CBC Section 1705.13.1 invoke for special inspection requirements?

  • a.TMS 602
  • b.ACI 318
  • c.AISC 341✓
  • d.ATC-20

CBC Section 1705.13.1 requires special inspection of structural steel seismic force-resisting systems in accordance with the quality assurance requirements of AISC 341. ACI 318 governs concrete, TMS 602 masonry construction, and ATC-20 is a post-earthquake evaluation procedure.

Seismic Detailing and Construction Quality Control

A design engineer notes during structural observation that hold-downs shown on the plans were omitted. What is the proper action under the CBC?

  • a.Wait until the final written statement is due, and only then list the item as an unresolved deficiency for the official
  • b.Revise the structural calculations so that the hold-downs are no longer needed at those locations
  • c.Report the deficiency in writing to the owner, the special inspector, the contractor and the building official✓
  • d.Direct the framing crew personally to install the hold-downs before the end of the working day

CBC Section 1704.6 calls for observed deficiencies to be reported in writing to the owner's representative, special inspector, contractor and building official. The observer does not direct the contractor's means and methods, and holding the report until the end defeats the purpose of observation.

Seismic Detailing and Construction Quality Control

Which nonstructural item requires periodic special inspection for seismic resistance in SDC D under CBC Section 1705.13?

  • a.Placement of furniture in open office areas
  • b.Painting of interior gypsum board partitions
  • c.Carpet installation over raised access floors
  • d.Anchorage of access floors and storage racks✓

CBC Sections 1705.13.5 to 1705.13.7 require periodic special inspection of items such as exterior cladding and veneer, access floors, anchorage of electrical and mechanical equipment for emergency systems, and storage racks over the height threshold. Finishes and furniture are not part of the program.