A 1/2-inch copper water line runs through a bored hole in a wood stud, and the edge of the hole is 1 inch from the face of the stud. Under IPC §305.6 the pipe must be protected by:

  • a.A steel shield plate at least 0.0575 inch thick (No. 16 gage)✓
  • b.A wrap of 10-mil tape wherever the pipe touches the stud
  • c.A plastic sleeve at least two pipe sizes larger than the tube
  • d.A wood block nailed across the face of the stud at the hole

Where piping other than cast iron or galvanized steel is less than 1-1/4 inches from the nearest edge of a framing member, the code calls for steel shield plates of No. 16 gage. Sleeves and tape address corrosion or abrasion, not nail and screw penetration, and a wood block will not stop a fastener.IPC §305.6

General Regulations

Shield plates protecting plastic or copper piping that passes through a wall plate must extend how far beyond the plate, measured above a sole plate or below a top plate?

  • a.At least 6 inches
  • b.At least 1/2 inch
  • c.At least 2 inches✓
  • d.At least 12 inches

The plates cover the area of the pipe where the member is notched or bored and extend at least 2 inches above sole plates and below top plates. Half an inch leaves the pipe exposed to toe-nailed fasteners; 6 and 12 inches exceed the requirement.IPC §305.6

General Regulations

Under IPC §306.3, backfill over a newly laid building sewer is placed in loose earth free of rocks and debris, in tamped layers of:

  • a.12 inches, until the pipe crown is covered by 24 inches
  • b.3 inches, until the pipe crown is covered by 6 inches
  • c.6 inches, until the pipe crown is covered by 12 inches✓
  • d.18 inches, until the trench is filled to finished grade

Backfill goes in 6-inch tamped layers until the crown of the pipe has 12 inches of cover, after which normal backfilling may continue. Thicker lifts cannot be compacted around the pipe haunches, and the other cover depths are not the code figures.IPC §306.3

General Regulations

A trench for a building sewer is dug parallel to a building footing. Under IPC §307.5, the trench must not extend:

  • a.Deeper than 12 inches unless an engineer has approved the trench
  • b.Below the 45-degree bearing plane from the bottom edge of the footing✓
  • c.Closer than 10 feet to the outside face of the footing at any depth
  • d.Within the property unless the footing has been underpinned first

Trenching parallel to footings and walls may not extend into the 45-degree bearing plane of the footing, because removing that soil undermines the load path. The code does not set a flat 10-foot distance, a 12-inch depth limit or require underpinning.IPC §307.5

General Regulations

According to the hanger spacing in IPC §308.5, horizontal PVC drainage pipe is supported at intervals of no more than:

  • a.6 feet
  • b.4 feet✓
  • c.12 feet
  • d.10 feet

PVC and ABS pipe are supported every 4 feet horizontally. Six feet applies to small copper tubing, 10 feet to larger copper tubing and to vertical plastic pipe, and 12 feet to steel pipe.IPC §308.5

General Regulations

Horizontal copper water tubing of 1-inch diameter is supported under IPC §308.5 at intervals of no more than:

  • a.4 feet
  • b.12 feet
  • c.6 feet✓
  • d.10 feet

Copper tubing 1-1/4 inches and smaller is supported every 6 feet; tubing 1-1/2 inches and larger every 10 feet. Four feet is the plastic DWV spacing and 12 feet is for steel pipe.IPC §308.5

General Regulations

Horizontal hubless cast-iron soil pipe in 10-foot lengths is being hung. Under IPC §308.5 the maximum hanger spacing is:

  • a.4 feet, the same as for plastic drainage pipe
  • b.20 feet, with a hanger at every second joint
  • c.10 feet, where 10-foot lengths of pipe are installed✓
  • d.15 feet, where 10-foot lengths of pipe are installed

Cast-iron pipe is supported every 5 feet, but the spacing may be increased to 10 feet where 10-foot lengths are used. Fifteen feet is the vertical spacing for cast iron, 4 feet is for plastic, and 20 feet is not allowed.IPC §308.5

General Regulations

PEX water tubing run horizontally is supported under IPC §308.5 at intervals of no more than:

  • a.120 inches
  • b.48 inches
  • c.72 inches
  • d.32 inches✓

PEX tubing is supported every 32 inches horizontally because it sags between supports when hot. Forty-eight inches is the PVC DWV spacing, 72 inches is for small copper tubing, and 120 inches applies to vertical runs.IPC §308.5

General Regulations

A finished DWV rough-in is tested with water under IPC §312.2. No section may be tested with less than:

  • a.A 20-foot head of water, held for 5 minutes
  • b.A 10-foot head of water, held for 60 minutes
  • c.A 10-foot head of water, held for 15 minutes✓
  • d.A 5-foot head of water, held for 30 minutes

Each section is filled so that it is under at least a 10-foot head of water, and the water is kept in the system for at least 15 minutes before inspection starts. The other heads and times are not the code values.IPC §312.2

General Regulations

An air test of a cast-iron drainage rough-in under IPC §312.3 is made at:

  • a.3 psi, held for 10 minutes
  • b.10 psi, held for 15 minutes
  • c.5 psi, held for 15 minutes✓
  • d.50 psi, held for 15 minutes

The DWV air test is 5 psi (10 inches of mercury) held without added air for 15 minutes. Three psi for 10 minutes is a fuel gas test value, and 50 psi is the air test for metallic water piping.IPC §312.3

General Regulations

Why does IPC §312.1 prohibit air testing of PVC and ABS drainage piping?

  • a.Compressed air dries the solvent cement and loosens the joints over time
  • b.Compressed air overheats the pipe wall and softens it below its rating
  • c.Compressed air stores energy, and a plastic pipe failure can throw fragments✓
  • d.Compressed air cannot reveal a leak that would be found by a water test

Plastic pipe can shatter under stored air pressure and send fragments across a job site, so the code bars air testing of plastic piping. Air does not harm cured solvent cement, it does find leaks, and it does not heat the pipe significantly.IPC §312.1

General Regulations

A site-built shower pan liner is tested under IPC §312.9 by plugging the drain and filling the pan with water to a depth of at least:

  • a.1 inch, measured at the drain, for 5 minutes
  • b.2 inches, measured at the threshold, for 15 minutes✓
  • c.4 inches, measured at the drain, for 60 minutes
  • d.6 inches, measured at the threshold, for 24 hours

The liner is flood tested with at least 2 inches of water at the threshold for not less than 15 minutes with no evidence of leakage. The other depths and times are not the code test.IPC §312.9

General Regulations

Under IPC §312.10, reduced pressure principle and double check backflow prevention assemblies are tested:

  • a.Every five years, when the water meter is exchanged by the utility
  • b.At installation, after repair or relocation, and at least annually✓
  • c.Monthly for the first year and every two years after that
  • d.At installation only, unless the water purveyor reports a problem

Testable assemblies are tested when installed, immediately after repairs or relocation, and at least once a year. A one-time test or a five-year interval would let a fouled check go unnoticed, and monthly testing is not required.IPC §312.10

General Regulations

A new copper water distribution system is tested under IPC §312.5 with water at:

  • a.Not less than 10 feet of head, held for 15 minutes at the top
  • b.Not less than the working pressure of the system, for 15 minutes✓
  • c.Not less than 300 psi, held for 2 hours with the meter closed
  • d.Not less than 5 psi above atmospheric pressure, for 15 minutes

Water supply piping is tested under a water pressure not less than the working pressure, or with air at 50 psi for piping other than plastic, for at least 15 minutes. Five psi and a 10-foot head are drainage test values; 300 psi is not required.IPC §312.5

General Regulations

Under IPC §314.2, a condensate drain from an air-conditioning coil must be at least what size and slope?

  • a.1-inch pipe sloped at least 1/16 inch per foot
  • b.1-1/4-inch pipe laid level to the discharge
  • c.3/4-inch pipe sloped at least 1/8 inch per foot✓
  • d.1/2-inch pipe sloped at least 1/4 inch per foot

Condensate drains are at least 3/4-inch internal diameter and slope toward the discharge at not less than 1/8 inch per foot. Half-inch line clogs with slime, and a level or 1/16-inch slope does not drain reliably.IPC §314.2

General Regulations

An auxiliary drain pan under an attic air handler, required by IPC §314.2.3, must be at least:

  • a.1-1/2 inches deep and 3 inches larger than the unit on each side✓
  • b.1 inch deep and the same length and width as the unit above it
  • c.1/2 inch deep and 1 inch larger than the unit on each side
  • d.3 inches deep and 12 inches larger than the unit on each side

The auxiliary pan is at least 1-1/2 inches deep and extends at least 3 inches beyond the unit or coil dimensions in width and length. A pan the size of the unit catches nothing at the edges, and the other dimensions are not the code values.IPC §314.2.3

General Regulations

A water pipe passes through an exterior concrete foundation wall. Under IPC §305.3, the pipe must be:

  • a.Cast directly into the concrete so that the wall holds it in place
  • b.Offset with two 90-degree elbows on the inside face of the wall
  • c.Run through a sleeve two pipe sizes larger, or under a relieving arch✓
  • d.Wrapped in a single layer of building paper and grouted in solidly

Pipe through a foundation wall is protected from breakage by a relieving arch or a pipe sleeve two pipe sizes greater than the pipe. Casting or grouting the pipe solid transfers settlement loads to it, and elbows do not protect it.IPC §305.3

General Regulations

Under IPC §305.1, metallic piping that passes through or under concrete or cinder walls and floors must be:

  • a.Increased one pipe size where it passes through the concrete
  • b.Changed to plastic for 5 feet on each side of the concrete
  • c.Protected against external corrosion by a sheathing or wrapping✓
  • d.Painted with two coats of oil-based enamel after installation

Pipe exposed to corrosive materials such as concrete, cinder or corrosive soil is protected by sheathing or wrapping that allows for movement. Upsizing, paint and a mandatory change to plastic are not the code's method.IPC §305.1

General Regulations

Under IPC §305.4, water service pipe in an area subject to freezing is installed at least:

  • a.6 inches deep and at least 2 inches below the frost line
  • b.12 inches deep and at least 6 inches below the frost line✓
  • c.36 inches deep and at least 18 inches below the frost line
  • d.24 inches deep, with no relation to the local frost line

Exterior water supply piping is installed not less than 6 inches below the frost line and not less than 12 inches below grade. The other pairs are not the code minimums.IPC §305.4

General Regulations

Where does IPC §301.6 prohibit the installation of plumbing piping?

  • a.In a corridor ceiling space above an exit passageway
  • b.In a mechanical room that contains a gas-fired boiler
  • c.In an elevator shaft or an elevator equipment room✓
  • d.In a parking garage below the building's first floor

Plumbing systems may not be located in an elevator shaft or elevator equipment room, apart from limited sump drainage provisions. Mechanical rooms, garages and corridor ceilings are ordinary locations for piping.IPC §301.6

General Regulations

A plumber finds a length of drainage pipe on the truck with no manufacturer's mark or standard printed on it. Under IPC §303, the pipe:

  • a.May be installed after the plumber marks it with a paint pen
  • b.May be installed if it is the same colour as the approved pipe
  • c.May be installed in vents but not in drains or building sewers
  • d.May not be installed, because materials must bear identification✓

Each length of pipe and each fitting must carry the manufacturer's identification and conform to the referenced standard; plumbing products also need third-party certification. Field marking, limiting use to vents and matching colour do not establish compliance.IPC §§303.1, 303.4

General Regulations

Under IPC §304, openings where pipes pass through an exterior wall of a restaurant must be:

  • a.Left open 1/2 inch all round so the wall cavity can ventilate
  • b.Fitted with a floor drain to carry away any wall condensation
  • c.Packed with fibreglass insulation and left without a cover
  • d.Sealed solid, or fitted with collars, so rodents cannot enter✓

The rodentproofing section requires openings for pipes in walls, floors and ceilings to be closed and protected so that rodents cannot enter. Open gaps and loose insulation give rodents a path, and a drain is unrelated.IPC §304

General Regulations

Under IPC §315.1, the annular space between a pipe and a sleeve through an exterior wall is:

  • a.Sealed with caulking or an approved flexible sealant✓
  • b.Left open so the pipe can expand and contract freely
  • c.Packed with oakum and molten lead on both sides
  • d.Filled solid with concrete so the pipe cannot move

Annular spaces at exterior penetrations are sealed with caulking material, foam sealant or a mechanical device; fire-rated assemblies are firestopped. Concrete locks the pipe in place, an open gap admits water and pests, and lead and oakum is a joint method, not a penetration seal.IPC §315.1

General Regulations

Who is responsible under IPC §107 for making plumbing work accessible and exposed for inspection?

  • a.The code official
  • b.The building owner
  • c.The pipe supplier
  • d.The permit holder✓

The holder of the permit keeps the work exposed and accessible until it is approved and notifies the code official when it is ready. The official inspects but does not uncover work, and owners and suppliers do not carry this duty unless they hold the permit.IPC §107

General Regulations

Under IPC §301.3, which fixtures and appliances must discharge to the sanitary drainage system?

  • a.Only fixtures in commercial buildings; dwellings may use an open ditch
  • b.Only fixtures on the lowest floor; upper floors may drain to the storm sewer
  • c.Only water closets and urinals; other fixtures may drain to the ground surface
  • d.All plumbing fixtures, drains and appliances that receive liquid wastes or sewage✓

Every fixture, drain, appurtenance and appliance used to receive or discharge liquid waste or sewage connects to the sanitary drainage system, directly or indirectly. Discharging to the ground, a storm sewer or a ditch is prohibited apart from approved gray water systems.IPC §301.3

General Regulations

A joist is notched to pass a drain line and the notch weakens the member beyond what the building code allows. Under IPC §307, the plumber must:

  • a.Fill the notch around the pipe with construction adhesive and sawdust
  • b.Finish the pipework and tell the framer after the rough-in inspection
  • c.Reduce the drain one pipe size so that a smaller notch can be used
  • d.Not cut the member that way; structural safety must be maintained✓

The structural safety section requires that cutting, notching and boring do not leave framing unsafe, and it refers to the building code limits. Leaving the damage, filling the notch or undersizing the drain are not acceptable answers.IPC §307.2

General Regulations

During construction of a building, IPC §311 requires that workers be provided with:

  • a.A laundry tray for washing tools and work clothing
  • b.Hot showers, with one shower for every ten workers
  • c.A drinking fountain on each floor under construction
  • d.Toilet facilities, maintained in a sanitary condition✓

Toilet facilities for construction workers are required, in the number and type set by the nonsewer waste disposal standard the code references. Showers, fountains on each floor and laundry trays are not required by this section.IPC §311.1

General Regulations

When soldering copper water tube, why is the tube end reamed after cutting?

  • a.To flare the tube so that solder is not needed at the fitting stop
  • b.To thin the tube wall so that it expands tightly into the fitting cup
  • c.To remove the burr that causes turbulence and erosion inside the tube✓
  • d.To roughen the outside of the tube so that the flux will stick better

A tube cutter rolls a burr into the bore; left in place it causes local turbulence that erodes the tube wall downstream. Reaming does not thin or flare the tube, and the outside surface is cleaned with abrasive, not a reamer.IPC §605 (soldered joints)

General Regulations

Which joint is made at the highest temperature?

  • a.A brazed joint, with filler metal melting above 840°F✓
  • b.A press-connect joint made with an elastomeric seal
  • c.A solvent-cemented joint made with primer and cement
  • d.A soldered joint, with filler metal melting below 840°F

Brazing uses filler metals that melt above 840°F but below the melting point of the parts joined; soldering is done below that temperature. Solvent cement and press fittings are made at ambient temperature.IPC §202

General Regulations

A plumber threads a length of galvanized steel pipe. Where should pipe-joint compound or tape be applied under the threaded joint rules of IPC §605?

  • a.On the female threads only
  • b.On both male and female threads
  • c.Inside the pipe at the cut end
  • d.On the male threads only✓

Thread lubricant, compound or tape is applied to male threads only, so that excess is pushed out of the joint, not into the waterway. Compound on female threads is forced into the pipe, where it can foul valves and aerators.IPC §605 (threaded joints)